CHAPTER SEVEN

TECHNOLOGY TRANSFER

Technology transfer is the process of moving the results of research and development from the laboratory into practice. FHWA has long been recognized as one of the world leaders in highway engineering technology and has always been very open and generous in sharing its knowledge and expertise with others. The FHWA’s current emphasis on implementation activities continues an evolution that began before the turn of the 20th century when its predecessor, the Office of Road Inquiry (ORI) was established. Research and technology transfer were two of the principal missions of the ORI and are, in fact, the oldest continuous FHWA activities.

Since the days of the ORI, the need for technology transfer in the highway program has become even more established. The FHWA Geotechnology Program has been cited by FHWA’s top management as a model for others to follow. The current program reflects the philosophies of the older programs that pioneered these activities, and utilizes some of the newer and more sophisticated ideas for marketing new technology into the 21st century.

The FHWA’s technology transfer mission is to ensure the timely identification and assessment of innovative research results, technology, and products, as well as the application of those that are determined to be of potential benefit to the highway community. These technologies and products are developed, implemented, and promoted with the FHWA’s partners in State and local agencies, private industry, universities, and others in the national and international highway communities.

It is clear that technology transfer has always been an integral part of the FHWA mission. Recently, the highway network in the United States has experienced numerous changes. The traffic on our highways has grown to the point that many of them routinely are congested. At the same time, the Interstate Highway System is virtually complete, and new highways are only infrequently being built, while many existing miles are wearing out. One answer to these concerns is introducing new technologies to the reconstruction, rehabilitation, and resurfacing of existing highways as well as to the construction of new highways. The Nation is faced with doing a better job with the highways that it has.

While the FHWA has a strong and growing technology transfer program across the United States, the success of the program is dependent on other public and private organizations advancing the agency’s efforts further in the highway community. The FHWA technology transfer process actually begins during the research and development stages when researchers begin to think about how and where their new technology will be phased into practice. A technology transfer specialist is brought in to thoroughly assess the research and development efforts to help devise an implementation strategy to get the research and development to the appropriate users.

In the case of existing technology that is developed by sources outside FHWA, the researchers become involved either in the identification process or later in the test and evaluation process. They also stay involved during the implementation and marketing stages to assist with any technical problems that may arise. A key step in the whole process is the identification of new and innovative technologies that have high potential for successful application in the United States highway program.

In addition to the normal avenues for discovery, the FHWA uses a "scouting" and "scanning" approach to technology discovery. Scouting is a military term that refers to the activities of a person or small group that goes on ahead of the main body to evaluate future prospects and gather information that will be useful for down the road decision making. Whenever our researchers and technology transfer specialists are visiting other domestic or foreign places of interest, they keep their ears and eyes open to learn about new technology that might be of interest and useful for possible application in the FHWA Geotechnology Program.

When an interesting new technology is discovered by one of our "scouts," a small group of experts is formed to conduct a "scanning" review. They begin by making an office engineering review and developing a plan to visit several organizations in one or more countries to gather detailed information. Sometimes, as part of these reviews and discussion, research and technology transfer partnerships are developed to further benefit the FHWA and its partner of choice.

In the case of new foreign technology that looks very promising, a plan of testing and evaluation will be developed to investigate the behavior and cost-effectiveness of these new techniques, materials, and/or equipment products. While these evaluations are going on, an implementation and marketing plan is also being developed. In some cases it may be necessary to conduct further field trials of these ideas, methods, practices, or products beyond the research testing and evaluation phase, in which case they are turned over to a special "Experimental Projects Program" for evaluation. This program is designed to encourage the construction of particularly promising experimental features to determine if they can be adopted for standard use in highway construction.

7.1 Demonstration Projects Program

Probably the most effective means of technology transfer is to conduct an actual demonstration of how the results of research can be applied to an actual operational situation. In most cases the field engineers do not have the time and resources to properly analyze useful research and translate it into operation. Demonstration projects allow researchers and technology transfer specialists to better communicate with those engaged in field projects. An official Demonstration Projects Program was established by FHWA in 1969 to promote and accelerate the widespread adoption and use of practical highway research results and their application to innovative engineering and construction practices.


7.2 Problems

The rapid development and increased use of special geotechnical techniques has not occurred without problems and setbacks. Also, the acceptance rate has not been uniform throughout the U.S. highway industry. Some agencies have been slow to adopt some or even any of the new methods, and some methods are very popular in some areas, but not in others. Although many reasons are given by agencies for their reluctance to accept the new technologies, the following are the most frequently cited:


A significant number of engineers are still not aware that some of these techniques exist. The lag time between the emergence of a new technology and its introduction into a certain geographical area varies, but on average it is too long. There has been some improvement since the 1980’s, but it must continue to improve in the current decade. The lack of adequate performance history has generated some reluctance in some highway engineers who usually tend to be conservative when it comes to using new products or techniques. Not many practitioners are quick to volunteer to be "pioneers" in the use of untested or unproven technology. Most would rather wait to see how things work out somewhere else. Of course, some tend to wait much longer than necessary.

In some foreign areas where the project "owner" is getting a long-term guarantee from the contractor, the demand for historical performance data is reduced. Historically in the U.S. highway industry, the owner assumes all risk once the project is accepted (shortly after construction is completed), as opposed to European practice where the contractor can be held accountable for the length of the guarantee period. Some U.S. agencies are testing this European practice to see how it works in their domain.

Another cause of implementation delays is that a few of these techniques have patents or other proprietary restrictions associated with their use. These proprietary controls can reduce the attractiveness of the techniques to some highway designers and, in some cases, become contractually awkward.

Still another cause of delay is the lack of suitable design aids. It is one thing to be aware that these methods exist, but quite another to be adequately informed about their proper use. Many situations have occurred where new techniques have been introduced to the profession without making available adequate design aids and construction guidelines. Unless the practitioners can see that user-friendly design tools are available, some will naturally shy away from using the new technology. Research and technology transfer efforts play an important role in reducing this reluctance on the part of the practitioners.

And finally, one of the biggest challenges facing the technology transfer program and implementation activities for geotechnical and ground treatment techniques is the elimination of various technical concerns expressed by the practitioners. For example, many are still concerned about the effect of corrosion on the design life of reinforced soil structures that use metallic materials as the reinforcing elements. By the same token, the durability of geosynthetic reinforcement material needs to be examined in greater detail. The lack of reliable quality control procedures for many ground treatment methods has discouraged their use in many cases. And overly restrictive environmental criteria have sometimes influenced decisions not to select particular ground treatment methods.

The lack of early consideration by the practitioners in the design process also makes a big difference. Too often these techniques are only considered as a last resort, which places them at a distinct competitive disadvantage.


7.3 Solutions

In an attempt to deal with these problems, the FHWA has developed a team approach utilizing personnel and resources from the Research, Development, and Technology Transfer programs to tackle these issues. Research has provided answers for developing improved methods and devices that practitioners can use to solve their problems. A series of demonstration projects have been established to show how the technology works. Technical experts from FHWA’s Operations offices are also very involved in this team approach and are available to provide technical assistance to the practitioners during the design and/or construction phases of any project. Funding is also made available to instruct, monitor, and report the results of new experimental features that are incorporated into the highway project. High-speed electronic communication and Internet availability of the FHWA technology information is also important to the implementation efforts.

Education and training are also an important part of this effort. Workshops and courses are developed and sponsored by FHWA’s National Highway Institute (NHI) to teach practitioners how to use the technology. Instructor’s handbooks and student workbooks have been prepared to aid the educators in conducting the training sessions. Slides, view-graphs, videotapes, and other training aids have also been developed for use in the courses. The FHWA geotechnical team of practitioners, researchers, and implementors provide expert guidance to the NHI staff members during development and conduct of these courses.
The main elements of the solution process can thus be summarized as follows:


7.4 Observations

In a multilevel government, a network encompassing Federal, State, and local government; universities; private industry; and highway organizations is critical to the speed of delivery and adoption of new technology. Technology transfer requires a structured program with champions from throughout the highway community who will convey the technology in innovative ways.

There must also be a simple vision that everyone can relate to and support; the new technology must make sense to the users and have a favorable cost-benefit. It also takes follow-up efforts to ensure that the technology progresses to all appropriate users, that those users have all the information they need to implement the technology, and that the technology is applied and becomes a part of the state of the practice. Additionally, the State must be permitted to be flexible and innovative; if users of the technology are not stifled, they will probably change what you give them into something better.

Technology transfer is just as important today as it was 100 years ago. The problems are just as real, and the need for solutions is just as pressing. Today, the technology is micropiles, geosynthetics, soil nailing, deep soil mixing, and other innovations we must have for the 21st century.


7.5 Examples of Success

The most direct and effective measure of success of any research effort is the application of research results in practice. During the past 10 to 15 years, the results of FHWA research in geotechnical areas have been incorporated into highway practice by the development of specifications and guidelines for the design of foundations, retaining walls, buried structures, and ground improvement techniques. The following brief summary will serve to highlight some of these contributions that have had a major impact on improving the state of the practice as well as the state of the art.

NCHRP Project 12-35; "Recommended Specifications for the Design of Foundations, Retaining Walls and Substructures" was initiated in 1989 with the intent of developing recommended revisions for sections 4, 5, and 7 of the AASHTO Bridge Specifications. The topical areas addressed during the project included spread footing, driven pile, and drilled shaft foundations (Section 4); gravity, semi-gravity, cantilevered, and anchored retaining walls, and mechanically-stabilized earth (MSE) and modular (or bin) wall systems (Section 5); and piers and abutments (Section 7). Project tasks included: (1) a data and literature search; (2) evaluating the information and preparing an outline for the recommended specifications; (3) submitting an Interim Report for comment by the review panel; (4) preparing the recommended specifications and commentary incorporating review comments; (5) identifying other articles of the Specifications affected by the proposed revisions; and (6) preparing a Final Report. The Final Report was submitted in 1990 and the recommended revisions were published as the 1991 Interims to the AASHTO Bridge Specifications.

The work completed for NCHRP 12-35 represents a significant testimonial to the value of FHWA’s geotechnical research program. At the time this work began, the AASHTO Specifications did not contain any articles or provisions for drilled shaft foundations, tolerable movements of bridges, or for retaining walls other than gravity walls. In fact, the provisions for retaining wall design were limited to a single page of the Specifications. As a result, whereas some portions of the work entailed only minor revision of the existing articles, others required substantial effort, including development of entirely new articles. The following sections highlight the application of this work, with emphasis on the contributions made by FHWA geotechnical research.

7.5.1 Foundations –  Revisions and additions to the provisions for the design of spread footings incorporate the results of Gifford, et al. (1987), Moulton, et al. (1985), Moulton (1986), and Lam and Martin (1986) (27,3,4,72). Gifford, et al. (1986) was directed toward documenting the settlement performance of bridge abutments and piers supported on spread footings founded on sand and using the data acquired to evaluate the accuracy of various published methods for estimating settlement of footings on granular soils (Article 4.4.7.2.2 Elastic Settlement). Moulton, et. al. (1985) and Moulton (1986) were referenced in Article 4.4.7.2.5 to provide guidance for estimating tolerable movements of simple- and continuous-span bridges when this type of information is not available from the bridge designer. Lam and Martin (1986), which describes procedures for developing ground and seismic parameters and for evaluating ground stability, is referenced in Article 4.4.10 for the design of footings subjected to dynamic and seismic loading.

Since the provisions for the AASHTO Specifications were relatively complete and well established for driven piles, the work consisted mostly of adding articles to incorporate recent analytical and technological developments. Principally, this consisted of research related to the design of laterally loaded piles (Reese, 1984), allowable stresses in piles during driving and under service loads (Davisson, et al., 1983), and the use of wave equation analysis (e.g., Goble, et al., 1986) to evaluate pile driveability (22, 11,12). Recommendations by Davisson, et al. (1983) to qualify allowable stresses under service loads based on the pile damage potential from subsurface conditions expected during driving were incorporated in the development of Article 4.5.7.3. Article 4.5.11 incorporates recommended maximum allowable driving stresses for steel and concrete piles recommended by Davisson, et al. (1983). Wave equation analysis (e.g., Goble, et al., 1986), which is used to model the soil-pile-hammer system, is included as Article 4.5.9 of the Specifications as a complement to the use of dynamic monitoring (Article 4.5.10) used to evaluate pile structural integrity, stress levels, pile and drive system performance, and pile capacity.

Because the design of drilled shafts was not addressed in previous editions of the AASHTO Specifications, all current provisions were developed as part of NCHRP 12-35. As a result, a substantial portion of the drilled shaft provisions incorporate design recommendations presented by O’Neill (73). This study resulted in the development of a manual describing design methods and construction procedures for drilled shaft foundations. In addition, reference is made in the articles to other FHWA-sponsored research, including Reese (74). Article 4.6.5.1 is a series of provisions for the geotechnical design of axially loaded drilled shafts in soil. The provisions are based on design procedures presented by Reese and O’Neill (1988), which incorporate the results of full-scale load tests on instrumented drilled shaft foundations. Provisions for considering the effects of group action (Article 4.6.5.2.4) and vertical ground movement (Article 4.6.5.2.5), such as from negative loading and expansive soil, were also developed from procedures presented in O’Neill (73) and Reese (74). Design for lateral loading is addressed in Article 4.6.5.6 and incorporates the results of Reese (74) as described previously, which can be used to evaluate the effects of shafts extending through sloping ground.

7.5.2 Retaining Walls –  As mentioned previously, the content of the previous edition of the AASHTO Specifications only addressed the structural design of gravity and semi-gravity retaining walls. Accordingly, the current AASHTO Specifications required development of entirely new provisions to supplement previous provisions, and to address the design of cantilevered and anchored retaining walls, and MSE and modular wall systems. Discussion below is limited to FHWA-sponsored research for anchored and MSE retaining walls.

The results of FHWA-sponsored research to develop design and construction guidelines (Christopher, et al., 1990) for MSE walls and the durability and corrosion behavior of reinforcements in these walls (Elias, 1990), were used to develop selected design provisions for the current AASHTO Specifications. Important additional guidance for the design of these walls was obtained from the results of NCHRP 24-2 (Mitchell and Villet, 1987). Christopher, et al. (1990) was used in developing provisions for proportioning wall structure dimensions for external stability (Article 5.8.1), the internal stability of inextensible and extensible reinforcements (Article 5.8.4.2), and the design for seismic loading (Article 5.8.10). Design life criteria presented in Elias (1990) were used in developing provisions for estimating corrosion losses for coated and uncoated steel reinforcements (Article 5.8.6.1), and for determining aging and construction damage losses for polymeric reinforcements (Article 5.8.6.2) (32,42).

In addition to the research references cited herein, supplemental information was obtained from the review of numerous other reports which present the results of various FHWA geotechnical research efforts. According to the author of the NCHRP 12-35 report, the results of FHWA-sponsored geotechnical research efforts were a very important component in the development of the revised specifications and guidelines. The most significant contributions were in the areas of spread footings, driven piles, and drilled shaft foundations, and anchored and MSE walls; areas that have received considerable attention during the past decade.


7.6 More Examples of Success

In addition to the incorporation of research results into practice, another measure of success is the cost-savings that can be attributed to the use of new and innovative geotechnical technologies. Such data are not easy to gather for a national perspective; however, a few States and some regions have made nominal efforts to quantify these savings.

In 1985, a special 1-day session titled "Cost Savings Through Geotechnology Transfer" was held in conjunction with the Northwest Geotechnical Workshop in Valdez, Alaska. The purpose of the session was to provide documented feedback on the "payoff" of FHWA geotechnology research and implementation efforts. The 10 northwestern States that normally participate in the yearly workshop were each asked to provide a minimum of 3 case history cost-saving examples. Forty-three cost-saving examples were presented with a combined savings totaling $76 million. Many of these examples involved ground treatment technologies that had been introduced to the region during the previous 5 years. These examples are a small random sampling that did not represent the full measure of cost-savings attributable to the FHWA efforts. However, it does give an indication of the significant "payoff" that is being realized.

In recent correspondence (1994) between the Secretary of the Washington State DOT and the FHWA, the Washington DOT engineers estimated that highway construction savings from the FHWA’s Durability of Geosynthetics study could be on the order of $70 million per year nationwide, which translated to $1 million to $2 million per year in savings for the State of Washington alone, based on current program levels. Considering that the current total cost of this research project is only $1.3 million, this appears to be a very profitable investment of research funds.

In another letter to FHWA from the Colorado Transportation Institute, it was noted that earth reinforcement technologies are a good example of actual and potential cost-savings that have resulted from FHWA research and implementation efforts. On the basis of their experience, they have conservatively estimated that State DOT’s can save approximately $700 million annually with full implementation.

In a feature article in the December/January 1992 issue of the Association of Drilled Shafts Contractors (ADSC) magazine called Foundation Drilling, the editor, Scot Litke, credited FHWA research with valuable contributions to improving the state of the practice and saving money. Mr. Litke is also the Executive Director of ADSC. The following excerpts from this article amplify these credits.


The "Research Review Board" referenced by Mr. Litke in the article is the "Geotechnology Research Specialty Committee" established by the FHWA program manager to assist in the decision-making process and planning for research programs. In addition to foundation specialists from industry, the committee also had representatives from FHWA field offices, SHA’s, ASCE, TRB and NSF.

In a November 20, 1996, letter from Mr. Litke, he quoted specific cost savings attributable to an FHWA research study, plus references to other successful studies funded by FHWA. The letter is re-printed herein.


In 1995, a series of letters were written to the Federal Highway Administrator, Mr. Rodney Slater, expressing concern over significant budget cuts and perceived downsizing of the Geotechnical Research Program. In addition to urging renewed emphasis on this area, these letters contained very flattering testimonials about the benefits received from previous FHWA efforts. These accolades came from other government agencies, private research institutes, academia, SHA’s and the private sector, in an effort to show their appreciation for the contributions made by FHWA to improve geotechnical engineering for highways, other transportation modes, and the Nation’s entire infrastructure program.

Brief excerpts are presented from a few of these letters to illustrate the broad support and respect for this program. They can be considered as one more measure of success.

Ms. Laurinda Bedingfield, Commissioner of the Massachusetts Highway Department, said:


Mr. James E. Roberts, Director of Engineering Services and Chief Structural Engineer for the California Department of Transportation, said:


Professor Frank Townsend, University of Florida, and President of the U. S. Universities Council of Geotechnical Engineering Research, which represents more than 100 universities said:


Dr. Robert M. Koerner, Director of the Geosynthetic Research Institute, said:


Professor Paul Mayne of Georgia Tech said:


Dr. Frazier Parker, Director of the Alabama Highway Research Center, said:


Dr. Ara Arman, Vice President of Woodward-Clyde Consultants, Inc., said:


Dr. William Marcuson, Director of the Geotechnical Lab at WES, said:


Professor Dov Leschinsky, University of Delaware, said:


Professor Fred Kulhawy of Cornell University said:


Dr. Mehmet Tumay, Director, Louisiana Transportation Research Center and former Director of the National Science Foundation Geotechnical Program, said:


Dr. Herbert H. Richardson, Director of the Texas Transportation Institute, said:


Dr. Ralph Trapani, President of the Colorado Transportation Institute, said:


Mr. Scot Litke, Executive Director of ADSC, said:


Professor Don DeGroot of the University of Massachusetts said:


Other letters of testimonial are also on file. From these letters and other reports and documents, it is clear that the FHWA program for research and technology transfer of geotechnical engineering is a vital service to improving highway design and construction, with valuable spin-off to other disciplines of civil engineering and infrastructure renewal. Although much has been accomplished, there is much more that needs to be done. With the recent establishment of the National Geotechnical Experimentation Sites, plus a group of research quality data bases, FHWA is now positioned to make even greater advances in geotechnology that will save many millions of dollars on future highway projects.