Introduction |
|
|
When developing a PRS for use in the field, the agency must make some
important pay adjustment-related decisions. One of these decisions
involves deciding whether to use Level 1 or Level 2 pay adjustment
procedures. If the agency chooses to accept as-constructed pavement using
Level 1 pay adjustment procedures, an appropriate lot composite pay factor
(CPF) equation must be determined. Finally, the agency must determine how
pay factors are to be limited when making final contractor pay
adjustments. This chapter is designed to provide the agency with the
information required to make these decisions.
Selecting a Pay
Adjustment Procedure (Level 1 or Level
2) |
|
|
The current revised PRS prototype specification allows the agency to
choose from two different pay adjustment procedures (representing the two
different PRS implementation levels). Level 1 is offered as a simplified
(and, therefore, more immediately implementable) method of estimating the
results obtained from Level 2. Table 9 reiterates some of the main
differences between the two PRS implementation levels.
Table
9. Key differences between PRS Level 1 and Level 2 pay adjustment
procedures.
Characteristic |
Level 1 |
Level 2 |
Primary Method of Acceptance Testing |
Current acceptance tests used by the agency. |
In situ acceptance testing is recommended. |
Included Acceptance AQC's |
Only those AQC's (of the available five)
historically measured by the agency for acceptance. |
Any or all of the five AQC's available for inclusion
in the PRS. |
Preconstruction Output |
Individual pay factor charts for each AQC. Each is
developed assuming that the other AQC's are held constant at their
target values. |
One simulated overall as-designed lot LCC
(reflecting the interactions between AQC's). |
Overall Lot Pay Factor Method |
Determined as a simple mathematical function of the
individual AQC pay factors (CPF equation). This CPF estimates the
pay factor obtained from the Level 2 direct simulation. |
Determined directly through simulation of all AQC's.
The closest simulation of actual field
conditions. |
It is strongly recommended that an agency gain experience with the
current PRS approach using Level 1. Although the Level 1 pay factor is
only an estimate of the computed Level 2 pay factor, at this time, the
Level 1 approach is by far the most practical of the two approaches as it
provides important preconstruction output desired by both the agency and
the contractor. After gaining experience with the Level 1 approach, an
agency may begin using the Level 2 approach or a combination of Level 1
and Level 2.
Defining a Level 1 Composite Pay Factor
Equation
It is recommended that the governing CPF equation be a simple
mathematical relationship of the independently determined AQC pay factors.
A number of different simple equation forms are currently used by agencies
to determine CPF equations. These same concepts may be used to determine
CPF's using the Level 1 PRS approach. Four specific CPF equation forms are
discussed in more detail in the following sections.
Weighted
Average
The weighted average CPF method involves
multiplying each calculated individual AQC pay factor by agency-chosen AQC
weighting factors. Each of the AQC weighting factors is "determined
through empirical observation or other engineering considerations," as
stated in the AASHTO Implementation Manual for Quality
Assurance.(28) Using this method, the resulting lot CPF is
determined using equation 18.
CPFLOT = å(PFn*Wn) / å(Wn)
(18)
where
CPFLOT = Calculated Level 1 lot
CPF.
n = Total number of AQC's included in the Level 1
specification (e.g., if the agency chooses to only include concrete
strength and slab thickness, then n =2).
PFn =
Independently determined Level 1 pay factors for each of the n AQC's
included in the Level 1 specification.
Wn =
Respective weighting factors for each of the n AQC's included in the
Level 1 specification.
An example illustrating the weighted average method is as follows:
Let's assume that the AQC's included in the specification consist of
concrete strength, slab thickness, entrained air content, and initial
smoothness. Therefore, the relevant calculation results are shown in
table 10. Substituting the appropriate calculated values into equation
18 gives the following:
CPFLOT = [å(PFn* Wn) / å(Wn)]
= [543.5 /
5.3]
= 102.5 percent
Therefore, for this example, the contractor would receive a pay
incentive equal to 2.5 percent of the submitted bid price.
Table 10.
Example calculations demonstrating the weighted average CPF
method.
AQC |
AQC number (n) |
Individual AQC PF (PFn) |
AQC PF Weighting Factor (Wn) |
PFn* Wn |
Concrete Strength |
1 |
106.5 |
1.3 |
138.5 |
Slab Thickness |
2 |
102.3 |
1.5 |
153.5 |
Entrained Air Content |
3 |
98.5 |
1.0 |
98.5 |
Initial Smoothness |
4 |
102.0 |
1.5 |
153.0 |
— |
— |
— |
å(Wn) =
5.3 |
å(PFn*Wn) =
543.5 | Note: PF =
pay factor.
Simple Average Method
The simple average CPF
method involves computing the average of the calculated individual AQC pay
factors. The resulting lot CPF equation is computed using equation 19.
CPFLOT = å(PFn) / n
(19)
where
CPFLOT = Calculated Level 1 lot
CPF.
n = Total number of AQC's included in the Level 1
specification.
PFn = Independently determined
Level 1 pay factors for each of the n AQC's included in the Level 1
specification.
An example illustrating the simple average method is as follows:
Assuming the same included AQC's and measured individual AQC pay
factors used in the weighted average method example, equation 19 then
becomes the following:
CPFLOT = å(106.5
+ 102.3 + 98.5 + 102.0) / 4
= (409.3) /
4
= 102.3 percent
Therefore, using the simple average method for this example, the
contractor would receive a pay incentive equal to 2.3 percent of the
submitted bid price.
Summation Method
The summation CPF method involves
summing the individual AQC pay adjustments (difference between the
computed AQC pay factor and 100 percent). The resulting lot CPF equation
is computed using equation 20.
CPFLOT = å(PFn – 100) + 100
(20)
where
CPFLOT = Calculated Level 1 lot
CPF.
n = Total number of AQC's included in the Level 1
specification.
PFn = Independently determined
Level 1 pay factors for each of the n AQC's included in the Level 1
specification.
An example illustrating the summation method is as follows:
Assuming the same included AQC's and measured individual AQC pay
factors used in the previous examples, equation 20 then becomes the
following:
CPFLOT = å(PFn – 100) + 100
= (106.5 – 100) + (102.3 – 100) + (98.5
–100) + (102.0 – 100) + 100
=
6.5 + 2.3 – 1.5 + 2.0 + 100
= 109.3 percent
Therefore, using the summation method for this example, the
contractor would receive a pay incentive equal to 9.3 percent of the
submitted bid price.
Product Method
The product CPF method involves
multiplying the individual AQC pay factors (expressed as decimals, e.g.,
103 percent = 1.03). The resulting lot CPF equation is expressed in
equation 21.
CPFLOT = (PF1 * PF2*
………*PFn) /(100)n-1
(21)
where
n = Total number of AQC's included in the Level 1
specification.
PF1 to PFn = 1 to n
independently determined Level 1 AQC pay factors.
An example illustrating the product method is as follows:
Assuming the same included AQC's and measured individual AQC pay
factors used in the previous examples, equation 21 then becomes the
following:
CPFLOT = (PF1 * PF2*
………*PFn) /(100)n-1
= (106.5 * 102.3 * 98.5 *
102.0) /1003
= 109.5 percent.
Therefore, using the product method for this example, the contractor
would receive a pay incentive equal to 9.5 percent of the submitted bid
price.
Selecting an
Appropriate CPF Method
The goal is to determine the overall lot CPF that represents the
performance that actually occurs over time. The Level 2 PRS simulation
gives the best available estimate of the true pay factor. Of the four CPF
methods presented in this section, the product method has typically been
found to most closely approximate this Level 2 pay factor. However,
agencies are encouraged to choose an appropriate CPF method after
conducting comparisons of the available CPF methods using the
sensitivity analysis portion of the PaveSpec 2.0
software.
Selecting Pay
Factor Limits |
|
| Although the agency indirectly limits
pay factors by defining appropriate MQL's for the quality of each AQC (see
the section titled Retesting
Procedures in chapter 5), an agency should also apply direct
limits to the calculated individual AQC pay factors, the overall lot pay
factor, or both. This pay factor limiting process is best explained using
examples.
Let's use the product method for illustration purposes.
For the chosen example, all five AQC's are included in the specification.
The assumed AQC pay factors for use in the example consist of the
following:
- Concrete Strength: PFSTR = 108.5
- Slab Thickness: PFTHK= 105.3
- Entrained Air Content: PFAIR = 99.5
- Initial Smoothness: PFSM = 96.4
- Percent Consolidation: PFCON = 102.4
The CPF for the lot (without applying any pay factor limits) is
calculated as the following, using equation
21:
CPFLOT = (PF1 * PF2*
………*PFn) /(100)n-1
= (108.5 * 105.3 * 99.5 *
96.4 * 102.4) /1004
= 112.2 percent
The following sections show the different methods by which this
calculated CPF of 112.2 percent may be limited.
Limiting the Overall Lot
CPF
The agency may choose to limit the overall lot pay
factor to an agency-chosen subjective value. For our example, let's assume
the agency feels that it cannot pay more than 106 percent of the bid price
due to budgetary limits. Therefore, the calculated lot CPF of 112.2
percent would be limited to the agency-chosen 106-percent value. For this
case, the contractor would then receive a 6-percent incentive payment for
the project.
Limiting Individual AQC Pay
Factors
Another approach for limiting pay factors for
budgetary purposes is to apply limits to the individual AQC pay factors.
For our example, let's assume that each of the individual AQC pay factors
is limited to 103 percent. Table 11 shows a comparison of the individual
AQC pay factors and resulting overall lot CPF's for both cases of with and
without applied AQC limits.
Table 11.
Example of limiting individual AQC pay factors (CPF calculated using
the product method).
AQC |
Individual AQC Pay Factors |
Without Limits |
All Limited to 103% |
Concrete Strength |
108.5 |
103.0 |
Slab Thickness |
105.3 |
103.0 |
Entrained Air Content |
99.5 |
99.5 |
Initial Smoothness |
96.4 |
96.4 |
Percent Consolidation |
102.4 |
102.4 |
Calculated Lot CPF |
112.2 |
104.2 |
Using the 103-percent individual AQC limits, the overall lot CPF is
then calculated to be 104.2 percent. For this case, the contractor would
then receive a 4.2-percent incentive payment for the project. |