BTS Navigation Bar

NTL Menu


Site Impact Traffic Evaluation (S.I.T.E) Handbook





Click HERE for graphic.




                             ACKNOWLEDGMENTS

Kellerco is most appreciative for the assistance rendered by U.S.
Department of Transportation, the Institute of Transportation
Engineers, and the staffs of several agencies throughout the country. 
U.S.D.O.T. staff who provided assistance included Ms. Louise Skinner,
Mr. Leroy Chimini, Mr. Carl Shear Mr. Christopher Fleet and Mr. George
Schoener.  Mr. Mark Norman of ITE provided valuable assistance.  Dr.
Everett Carter and Mr. Abdulla Meer acted as consultants to Kellerco. 
Mr. Sanjeev Mathotra provided research assistance on the study.  Mr.
Joe Mehra was the Principal Investigator and Mr. C. Richard Keller was
the Principal-In-Charge.



                            TABLE OF CONTENTS
                                                                Page No.

   I.   INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . 1

        BACKGROUND   . . . . . . . . . . . . . . . . . . . . . . . . . 1

        ORGANIZATION OF REPORT . . . . . . . . . . . . . . . . . . . . 3

  II.   OVERVIEW OF SITE ACCESS STUDY PROCESS. . . . . . . . . . . . . 5

 III.   SITE ACCESS STUDY PROCESS. . . . . . . . . . . . . . . . . . .11

        PHASE I.    ESTABLISH STUDY DESIGN AND VERIFY EXISTING PEAK
                    HOUR TRAFFIC . . . . . . . . . . . . . . . . . . .11

        PHASE II.   PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION
                    WITHOUT SITE DEVELOPED . . . . . . . . . . . . . .20

        PHASE III.  PROJECT PEAK HOUR SITE DEVELOPMENT
                    TRAFFIC. . . . . . . . . . . . . . . . . . . . . .23

        PHASE IV.   PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION
                    WITH SITE DEVELOPED. . . . . . . . . . . . . . . .24

        PHASE V.    DEVELOP SITE ACCESS RELATED SOLUTIONS. . . . . . .27

        PHASE VI.   NEGOTIATE SITE ACCESS. . . . . . . . . . . . . . .29

        PHASE VII.  IMPLEMENT PROJECT ACCESS IMPROVEMENTS. . . . . . .30

  IV.   CONCLUSIONS  . . . . . . . . . . . . . . . . . . . . . . . . .33

     SUMMARY OF CASE STUDIES . . . . . . . . . . . . . . . . . . . . .34

APPENDICES

        A    DEFINITIONS:  SITE ACCESS STUDY TERMINOLOGY
        B    ISSUES AND TRENDS IN SITE ACCESS STUDIES
        C    TECHNICAL BACKGROUND
        D    CASE STUDIES

                                   iii


                             LIST OF FIGURES

Number                                                              Page

     1  Flowchart of Site Access Study Process . . . . . . . . . . . . 6
     2  Summary of Basic Site Access Study Process . . . . . . . . . . 8
     3  Frequency of Complex Issues Occurring In Typical
        Site Access  . . . . . . . . . . . . . . . . . . . . . . . . .10
     4  Typical Parameters For A Basic Site Access Study . . . . . . .13

   4a   Typical Parameters For A Complex Stage I (+5 Years)
        Site Access Study For A Proposed . . . . . . . . . . . . . . .15

   4b   Typical Parameters For A Complex Stage II (+10 Years)
        Site Access Study For A Proposed Mall. . . . . . . . . . . . .16

   4c   Typical Parameters For A Complex Stage III (+20 Years)
        Site Access Study For A Proposed . . . . . . . . . . . . . . .17

    5   AM Peak Hour Level Of Service Comparison For
        Intersection . . . . . . . . . . . . . . . . . . . . . . . . .26

Appendices
  C-1   Example Of Geographic Distribution Of Office
        Building Generated Trips During AM Peak Hour . . . . . . . . C-7

  C-2   Example Of Geographic Distribution Of Site Generated
        Traffic, As A Percent of Total Inbound Trips Generated For
        Short, Mid Term and Long Term Road Networks. . . . . . . . . C-8

  D-1   Case Study No.1 Site Location And Road Network . . . . . . . D-3

  D-2   Case Study No.1 "A" Trip Distribution For Office and Motel
        Generated Trips
        (Existing Situation And Conditions 1, 2, & 4). . . . . . . . D-8

  D-3   Case Study No.1 "B" Trip Distribution For Office And
        Motel Generated Trips (Condition 3). . . . . . . . . . . . . D-9

  D-4   Case Study No.2 Site Location With Respect To Road
        Network      . . . . . . . . . . . . . . . . . . . . . . . .D-13

                                   iv



                       LIST OF FIGURES (Continued)

Number                                                              Page

  D-5   Case Study No.2 Geographic Distribution Of Site
        Location     . . . . . . . . . . . . . . . . . . . . . . . .D-14

  D-6   Location Of Case Study No.3 Site With Respect To
        Area Road    . . . . . . . . . . . . . . . . . . . . . . . .D-21

  D-7   Case Study No.3 New Development Anticipated By
        1987         . . . . . . . . . . . . . . . . . . . . . . . .D-23

  D-8   Case Study No.3 General Geographic Distribution. . . . . . .D-25

  D-9   Case Study No.3 1987 Road Network. . . . . . . . . . . . . .D-26

 D-10   Case Study No.4 Site Location And Road Network . . . . . . .D-31

                                    v


                             LIST OF TABLES

Number                                                              Page

  B-1   Market Shifts In The . . . . . . . . . . . . . . . . . . . . B-4

  C-1   Example Of Technique For Estimating office Building
        Peak Hour Generated Trips. . . . . . . . . . . . . . . . . . C-3

  D-1   Case Study No.1 Alternative Conditions Evaluated . . . . . . D-7

  D-2   Case Study No.1 Peak Hour Level Of Service Comparison
        1 For Conditions 1,2,3,4 . . . . . . . . . . . . . . . . . .D-11

 D-3a   Case Study No.2 AM/PM Peak Hour Trip Generation
        Rates By Land Use For Alternative Conditions . . . . . . . .D-15

 D-3b   Case Study No.2 AM/PM Peak Hour Comparison of
        Traffic Generated For Alternative Condition. . . . . . . . .D-16

  D-4   Case Study No.2 Condition 5 Internal/External
        Traffic      . . . . . . . . . . . . . . . . . . . . . . . .D-18

  D-5   Case Study No.2 Peak Hour Level of Service
             Comparison for Condition 1 thru 5 . . . . . . . . . . .D-19

  D-6   Case Study No.3 Site Generated AM/PM Peak Hour
        Volumes      . . . . . . . . . . . . . . . . . . . . . . . .D-24

  D-7   Case Study No.3 Peak Hour Level of Service
        Comparison for Conditions 1 thru 4 . . . . . . . . . . . . .D-28

  D-8   Case Study  No.4 Base Condition A. . . . . . . . . . . . . .D-33

  D-9   Case Study  No.4 Condition B . . . . . . . . . . . . . . . .D-34

 D-10   Case Study  No.4 Condition C . . . . . . . . . . . . . . . .D-35

 D-11   Case Study  No.4 Condition D . . . . . . . . . . . . . . . .D-36

 D-12   Case Study  No.4 Condition E . . . . . . . . . . . . . . . .D-37

 D-13   Case Study  No.4 Condition F . . . . . . . . . . . . . . . .D-38

                                   vi



                       LIST OF TABLES (Continued)

Number                                                              Page

 D-14   Case Study No.4 Condition G. . . . . . . . . . . . . . . . .D-39

 D-15   Case Study No. 4 Peak Hour Level of Service
        Comparison For Condition A Thru G. . . . . . . . . . . . . .D-41

                                   vii





I. INTRODUCTION

A "site access study" is a generic term commonly used by
transportation/land use planners and traffic engineers to describe how
traffic generated by either new land use(s) or replacement land use(s)
will be served by an existing or future road network. [1]

Since the technical analyses allow for the effect of site generated
traffic on the road network, the term "traffic impact" has been
frequently applied to this study process.  While "traffic impact" may
be of interest it is not the only reason for such studies, and
therefore the term "site access study" is considered more appropriate.

BACKGROUND

A site access study involves technical analyses applied to a distinct
study area which may range from one or two key intersections to a
complete roadway network encompassing numerous intersections and
interchanges; and occasionally extending a mile, or several miles,
from the specific site.  Since the study is usually related to land
use regulations, the principal reviewing agency is usually a city,
town, township, or county.  A regional agency such as an MPO
(Metropolitan Planning Organization) will have an assisting or
coordinating role in most cases.  State agencies usually review the
findings to satisfy responsibilities for major public facilities i.e.
State or Federal roadways water, utilities environmental impact? etc. 
The regional agency is often used as a data resource insofar as travel
demand and land use projections are concerned.  Since a site access
study is usually performed at a local or subarea level, areawide data
are not directly applicable to the type of analyses needed to perform
a site access study. it is, becoming increasingly important for the
regional agency to maintain a record of the roadway improvements
implemented as a result of site access studies.  Significant changes
are sometimes made in the regional road network, which may influence
regional travel analyses.

Since the site access study process is being used more and more as a
basis for establishing a developer's share of future roadway
improvements, the technical analyses are increasingly being used for
negotiations between public and private groups (See Appendix B for a
discussion of the issues and trends related to site access studies). 
This places great importance on certain elements of the technical
analyses, such as trip
____________________

[1].  See Appendix A for definitions of site access terminology

                                    1



generation rates, trip distribution patterns mode split analyses and
the percentage of site trips arriving or departing during the peak
hour.  The emphasis on privately financed improvements or
contributions has also led to the extension of the study area
boundaries to ensure that the widest range of public concerns are
included.  In any event, site development projects contribute very
significant roadway improvements to the benefit of both the
development and the public.  Of course, the extent of the improvement
varies by size of the project.  In addition, financial contributions
are frequently made to a general "subarea" roadway improvement fund on
the basis of the density (trips generated) of the proposed
development.  The public-private negotiation process primarily
involves commercial-retail development.  Financial aspects of
residential development apparently preclude significant financial
roadway commitments beyond site related roads.

A site access study may be performed for a basic condition or a very
complex condition.  For example, a basic condition would refer to a
small retail store or day care center to be built on a one acre tract
and occupied within one year.  A complex condition would refer to a
major development such as a 100-acre tract with 3 to 4 million square
feet of mixed use development consisting of hotels, office buildings a
retail mall and residential units.  Full occupancy may not occur for
10 to 15 years, The same basic technical analyses apply to both
conditions.  The 100-acre tract involves more complex issues and
therefore involves more detailed technical analyses and the need for
professional experience.

The technical analyses which constitute a site access study are
usually performed by either a transportation planner or traffic
engineer, acting as a consultant, with the study cost being paid by
the developer of the subject tract.  Occasionally, the studies are
performed by consultants for public agencies such as a town, city, or
county either in lieu of a developer's study or as an independent
study for comparison to a developer's study if sufficient agency staff
are not available.  Sometimes the developer will be required to
reimburse the public agency for the site access study.

This report was prepared to promote a better understanding of the site
access study process.  While such studies have been conducted
throughout the U.S. for many years, there is very little technical
documentation of the basic study process or general guidelines.  This
has probably occurred because the studies are usually performed to
satisfy local zoning (where applicable), ordinances or land use
regulations; and their technical content varies to the extent
necessary to resolve

                                    2



conflicting issues.  Due to the variation in state and local land use
regulations, the information contained in this report should be
considered as a general guideline only.  The technical analyses and
procedures described should be altered to satisfy specific regulations
as applicable to: 1) a specific site development plan and 2) local and
state land use regulations.

ORGANIZATION OF REPORT

This report describes the basic site access study process, and the
technical implications which tend to create a complex site access
study.  The remainder of the report is organized as follows:

   -  Chapter II presents an overview of the site access study
      process,  The seven phases of the process are cross referenced
      in Chapter III.

   -  Chapter III describes the seven phases of the basic site access
      study process.  Variations for a complex study are also
      discussed.

   -  Chapter IV presents the conclusions and a summary of the four
      case studies described in Appendix D.

   -  Appendix A presents definitions of the terminology used in site
      access studies.

   -  Appendix B discusses the issues and trends related to site
      access studies.

   -  Appendix C presents a description of the trip generation, trip
      distribution/assignment and level of service procedures used in
      a site access study.

   -  Appendix D presents four case studies which illustrate the use
      of trip generation rates and the sensitivity of trip generation
      rates with respect to certain elements of the site access study
      process.

                                    3



                 [ This page intentionally left blank I

                                    4



II. OVERVIEW OF SITE ACCESS STUDY PROCESS

The site access study process is depicted in the flowchart in Figure
1. Each of the seven phases of a basic study are summarized in more
detail in Figure 2.

Phase I establishes the study design based on discussions and
agreements with local officials.  Data collection and/or analyses then
result in the verification of the existing background traffic
situation and peak hour levels of service.

Phase II uses Phase I existing background traffic and inputs from
regional systems planning and/or local/state agencies to estimate
future background traffic without the site developed.  The traffic
generated by other new developments adjacent to the site are forecast
using trip generation, distribution and assignment procedures as
described in Appendix C. The levels of service without the site
developed can be estimated by combining future background traffic and
traffic for new adjacent sites.

Phase III deals exclusively with site specific generated traffic,
organizing the data in a format so it can be combined with Phase II
data.  This phase is similar to the forecasting of traffic for the
other new adjacent sites performed in Phase II.

Phase IV establishes the peak hour situation with the site fully
developed and occupied.  The Phase IV total traffic is estimated by
combining the results of Phase II and Phase III.  The Levels of
Service (LOS) with the site traffic are then estimated.  A comparison
of the LOS between Phase II and Phase IV results shows the impacts of
the site traffic.  The comparison of Phase II (without the site
developed) to Phase IV (with the site developed) is not always
sufficient.  With the site developed may mean "as-zoned" or "as-
proposed" leaving two options to be studied rather than one.  Whether
or not this strategy is pursued is an administrative decision often
based on negotiations.

Phase V is a creative process which identifies and analyzes alter-
native site access related improvements.  While this phase usually
involves a roadway or traffic operational improvement (such as changes
to signal phasing or the addition of turn lanes), it may also include
major roadway improvements or Transportation Systems Management (TSM)
actions to limit or reduce peak hour traffic.  The alternative
solutions are evaluated for peak hour effectiveness.  The study
findings (Phases I through V) are then documented for review by the
local officials.

                                    5



                                 FIGURE
                 FLOWCHART OF SITE ACCESS STUDY PROCESS
                                 PHASE I


Click HERE for graphic.

____________________

   1/ See Appendix C for technical procedures

                                    6



The negotiations between local officials and the developers are
carried out in Phase VI.  During negotiations with local officials the
solution may change significantly, requiring additional analyses. 
Further issues may be raised which were not addressed in the original
analysis, regarding TSM actions for reducing peak hour traffic, or
developer sponsored ridesharing programs or shuttle bus/van service. 
This can lead to more detailed analyses, modification of the original
LOS results, and a change in site access related improvements. 
Supplemental technical analysis may be needed to resolve outstanding
issues with citizen groups who are interested in average daily
traffic.  The peak hour based analyses can then be modified to
represent the change in 24 hour "daily" volumes on key road links
without and with the site developed.

Phase VII is the implementation phase, which occurs after agreement is
reached between the developers and the local officials.  Authorization
by the local officials is usually in the form of a permit to construct
the improvements or to provide funds for all or a share of the
improvements.  TSM actions such as ridesharing or shuttle bus service
may also be provided by the developer.  Final site plans and road
construction plans are then provided by the site engineer and
architect.  Parking facility (lots, garage, decks), circulation and
entrance details are particularly important.  If the developer is
responsible for the signalization of an intersections), installation
plans and specifications are developed for review by state and local
officials.

The basic site access process can change significantly for a complex
site access study.  This not only increases the study cost, but also
extends the study time frame.  The technical issues associated with a
complex study are discussed for each appropriate phase in the next
Chapter.  These issues are summarized in Figure 3 along with the
probability of the issue being raised in a typical re-zoning case for
three typical land use options.  The frequency of occurrence depends
on a variety of site specific issues other than size.  Also noted by a
(+) are the items considered to be on an increasing trend.  This is
possibly due to an increased awareness and knowledge of attributes     
of the technical process, on the part of local officials, developers
transportation planners or traffic engineers.  Large tracts have
always been more complex to study, but two recent trends have placed
more emphasis on such studies: the more accessible large tracts have
been developed, leaving the more difficult large tracts to be
developed; the financial or economic situation may influence the
tendency to develop larger tracts more intensely than in the past.

                                    7



                                FIGURE 2
               SUMMARY OF BASIC SITE ACCESS STUDY PROCESS

                                                                    Page
  Topic                                                              No.

PHASE I.     ESTABLISH STUDY DESIGN AND VERIFY EXISTING PEAK HOUR
             TRAFFIC

  * Confirm Site Development Program . . . . . . . . . . . . . . . . .11
  * Meet with Local Officials to Establish Study Area
    and Parameters . . . . . . . . . . . . . . . . . . . . . . . . . .12
  * Establish Study Design Parameters. . . . . . . . . . . . . . . . .12
  * Evaluate Data Needs. . . . . . . . . . . . . . . . . . . . . . . .18
  * Collect New Data (Optional). . . . . . . . . . . . . . . . . . . . .
19
    Tabulate Data; Calculate LOS [1] . . . . . . . . . . . . . . . . .19
  * Identify Site Access/Circulation Constraints and Opportunities . .20

PHASE II.    PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION WITHOUT SITE
             DEVELOPED

  * Establish Past Growth Rate in Key Corridor(s). . . . . . . . . . . .
20
  * Identify Changes in Road Network and Land Use Type/Density . . . .21
  * Project Phase I Peak Hour Traffic to Future Study Year . . . . . .22
  * Calculate Level of Service . . . . . . . . . . . . . . . . . . . .22
  * Identify Changes between Existing and Future Situation . . . . . .23

PHASE III.  PROJECT PEAK HOUR SITE DEVELOPMENT TRAFFIC

  * Select and Apply Appropriate Trip Generation Rates . . . . . . . .23
  * Determine Trip Distribution Pattern and Assign
    Trips to Road Network. . . . . . . . . . . . . . . . . . . . . . .24

PHASE IV.    PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION WITH SITE
             DEVELOPED

  * Combine Phase II Background Traffic with Phase III Assigned
    Traffic to Achieve Total Peak Hour Traffic . . . . . . . . . . . .24
  * Calculate LOS; and Compare to Phase I and
    Phase II LOS Results . . . . . . . . . . . . . . . . . . . . . . .24
  * Identify Changes between Phase If Phase II and
    Phase IV Results . . . . . . . . . . . . . . . . . . . . . . . . .25
____________________

[1] LOS - Level Of Service- as related to the level of intersection
operating efficiency

                                    8



                          FIGURE 2 (continued)
               SUMMARY OF BASIC SITE ACCESS STUDY PROCESS

                                                                    Page
  Topic                                                              No.

PHASE V.     DEVELOP SITE ACCESS RELATED SOLUTIONS

  * Evaluate Alternative Solutions to Achieve Acceptable
    Levels Of Service. . . . . . . . . . . . . . . . . . . . . . . . .27
  * Select Preferred Solution; Document Findings . . . . . . . . . . .28

PHASE VI. NEGOTIATE SITE ACCESS

  * Begin Negotiations between Local Officials and
    Developers to Reach Agreement on the Proposed Development. . . . .29
  * Perform Supplemental Technical Analyses to
    Resolve Outstanding Issues . . . . . . . . . . . . . . . . . . . .29

PHASE VII. IMPLEMENT PROJECT/ACCESS IMPROVEMENTS

  * Assist Site Engineer in Preparing Construction Plans . . . . . . .30
  * Develop Signalization Plans/Specifications
    (If Applicable) for Bid. . . . . . . . . . . . . . . . . . . . . .30
  * Privately Funded Roadway or Traffic Operational
    Improvements Implemented . . . . . . . . . . . . . . . . . . . . .31

                                    9



                                FIGURE 3
                  FREQUENCY OF COMPLEX ISSUES OCCURRING
                     IN TYPICAL SITE ACCESS STUDIES

                                                             110 Acre
                              One Acre                       Mixed Use
                            Free Standing     40 Acre      Office-Hotel
   ISSUES                       Store       Retail Mall    Mall Complex

   PHASE I
 + 10 to 15 year build-        seldom         seldom        frequently
   out requires interim
   stage analyses
 + Special survey needs        seldom      occasionally     frequently

   PHASE II
 * Significant changes in      seldom      occasionally     frequently
   road network
 + Significant new land        seldom      occasionally    occasionally
   use near subject site
 + Major site related           never         seldom          usually
   improvements require
   20 year analysis

   PHASE III
 + Physical site charac-       seldom         seldom       occasionally
   teristics restrain
   site access
 * Hybrid land use          occasionally      seldom       occasionally
   option requires trip
   generation research
 * Expansion of retail           NA        occasionally       seldom
   mall requires trip
   linking research
 
   PHASE IV
 + As-zoned vs. proposed    occasionally   occasionally     frequently
   analyses required

   PHASE V
 + LOS comparison              seldom      occasionally       usually
   requires careful
   solution development

   PHASE IV
 + TSM actions require         seldom         seldom       occasionally
   further analysis
 * ADT traffic analyses     occasionally   occasionally    occasionally
   required

   PHASE VII
 + Developer implements        seldom       frequently      frequently
   access improvements

 "+" indicates items which appear to be on an increasing trend

                                   10



III.  SITE ACCESS STUDY PROCESS

This chapter discusses each of the seven phases of the site access
study process.  The discussion follows the general outline presented
in Figure 1. The technical guidelines associated with each of the
seven phases of a basic site access study are described in this
chapter.  Variations for a complex site access study are noted where
applicable.

PHASE I. ESTABLISH STUDY DESIGN AND VERIFY EXISTING PEAK HOUR TRAFFIC

Phase I of the site access study process results in the establishment
of a study design based on discussions and agreements with the local
officials.  Further, the data collection efforts are carried out in
this phase resulting in the verification of the existing peak hour
traffic situation in the defined study area.  The various steps in
Phase I of the site access study process are described below.

Confirm Site Development Program

Perform a field reconnaissance of the site during peak traffic
conditions.  Meet to discuss with the developer and other members of
the project team the following site related items: [2]

   -  proposed land use type/density including staging
   -  current zoning classification and allowable land use/density
   -  year project will be fully developed/occupied
   -  basic site access constraints/opportunities ( e.g. easements
      right-of-way, etc.)
   -  available site plans
   -  development program strategy/schedule
   -  on site circulation ingress/egress points, building locations,
      parking lots, garages/decks (to the extent information is
      available)
   -  complex studies will require discussion of long term
      implications and may need 10-,15-, and/or 20-year analyses
      because of the length of the buildout period.
____________________

[2].  "Project Team members" vary depending on the purpose of a study. 
They may include: attorney; architect; site engineer; landscape
architect; transportation planner; traffic engineer; site planner;
and/or developer.



   *  Meet With Local Officials To Establish Study Area And Parameters

Typical parameters include:

   -  planned and committed road/traffic operational improvements;
      land use developments (type, density and location); and site
      implications
   -  subject site relationship to adjacent land uses/roadways
   -  study area boundary definition; key intersections and special
      traffic operational issues
   -  applicable peak hour turning movement counts and 24 hour traffic
      volumes for 3 to 5 year period
   -  applicable public facilities design standards
   -  traffic signal turning/phasing for key signalized intersections
      to include interconnection
   -  applicable roadway construction plans for geometrics and right-
      of-way
   -  applicable comprehensive plan elements
   -  technical procedures for calculating Level of Service
   -  access/circulation issues of particular concern, including
      Possible citizen issues
   -  special data needs for unusual land uses or access problems.

Establish Study Design Parameters

This is probably the most critical task after discussions with both
the developer and local officials have taken place.  Interpretation of
the most potentially relevant issues requires considerable experience
for larger tracts; and occasionally for small tracts due to unusual
circumstances.  This task should encompass both a graphic critique and
workshop type discussion of key issues, with the technical analyses
designed to resolve critical issues.  Figure 4 illustrates typical
parameters of concern for a basic study accomplished within six
months.

First consider the study area boundary and include sufficient area to
ensure that technical issues will most likely be resolved.  As
illustrated a basic study may only encompass two intersections and a
site entrance.  At each intersection, items such as lane
configuration, geometrics, signal timing and phasing, and peak hour
queues should be considered as applicable.  Changes in the road
network over buildout time frames are particularly important because
the nature and extent of site access may change significantly.  Key
road corridors should be selected and potential (other) land use
developments noted by location and density.

                                   12



                                FIGURE 4
            TYPICAL PARAMETERS FOR A BASIC SITE ACCESS STUDY


Click HERE for graphic.


                                   13



The effect of one way roads should be considered by evaluating inbound
(to the site) and outbound (from the site) access routes for site
generated peak hour trips.  For example, inbound site access routes
may not be the reverse of outbound routes due to the road network
configuration.  As illustrated in Figure 4, if the site had a second
access route to point Al two additional intersections B and C. might
have been selected if the tract generated significant traffic at all
four intersections.

Historical 24 hour ADT data needs (obtained from the state highway
departments or local agencies) would be considered along with citizen
issues associated with ADT projections.  Unusual site related
facilities such as toll roads, pending development projects with
planned road improvements new subway or rail facilities, new bus
service etc. should be considered with respect to their effect on site
access, on both a short and long term basis.

Since a complex site access study encompasses a larger study area and
a larger more complex development, it will involve more road links and
new area land developments.  Figures 4a, 4b and 4c were prepared to
compare the basic study in Figure 4 to a more complex three stage site
access study featuring +5, +10 and +20 year conditions for a new mall
project.

Figure 4a shows a mall development with a +5 year road network which
is achieved by considering the existing roadways plus planned/
committed public improvements plus site related improvements.  Natural
ly if the short term peak hour situation is being studied without the
subject site being developed site related roadway improvements would
be deleted from this road network.  Figure 4a also shows additional
(committed and planned) development anticipated near the site during
the short term period.  Peak hour traffic for this additional
development should be generated, distributed and assigned to the road
network.  Besides the site and additional development trips, corridor
traffic would be increased (by the growth rates indicated) to account
for new development beyond the study area.  The resultant corridor
volumes can then be compared to areawide traffic projections if they
are available.  Usually this modeling process presents a realistic
view of the most probable short term situation for detailed peak hour
analyses.

Figure 4b shows Stage II of the subject site development during the +5
to +10 year period.  Again the road network changes with various road
improvements, and additional new study area development is identified.

Figure 4c shows the +20 year regional situation with additional

                                   14



                                FIGURE 4a
        TYPICAL PARAMETERS FOR A COMPLEX STAGE I (+5 YEARS) SITE
                    ACCESS STUDY FOR A PROPOSED MALL


Click HERE for graphic.


                                   15



                                FIGURE 4b
       TYPICAL PARAMETERS FOR A COMPLEX STAGE II (+10 YEARS) SITE
                    ACCESS STUDY FOR A PROPOSED MALL


Click HERE for graphic.


                                   16



                                FIGURE 4c
       TYPICAL PARAMETERS FOR A COMPLEX STAGE III (+20 YEARS) SITE
                    ACCESS STUDY FOR A PROPOSED MALL


Click HERE for graphic.


                                   17



subject site development.  Now the areawide traffic projections are
probably available for the site development study projection years,
although differences may still arise regarding long range road
improvements; i.e. will these roads actually be built in 20 years?

Fundamentally, once this 20 year site access study is completed for a
large site, it serves two purposes:

   -  Very specific site related access issues can be firmly
      understood and alternatives clearly evaluated to improve the
      decision making process regarding the subject site.
   -  Local officials can understand the relationship of the site
      related improvements to the subarea road network and the need
      (priority) for publicly funded road improvements, in combination
      with privately funded projects.  In this way the privately
      funded site access study facilitates subarea and even regional
      road link decisions.

*  Evaluate Data Needs

Having determined the study parameters, based on the project team and
local official comments available data are evaluated to determine if
new data needs to be collected.  New data collection is very much
related to site access study needs and can vary significantly.

Examples of basic and complex study issues are described below as they
relate to data needs.

Basic Site Access Study For An Office Building

   -  Perform 6 to 9 AM and 4 to 7 PM peak hour turning movement
      counts at key study area intersections since they represent the
      peak hour of the generator as well as the peak hour of the
      adjacent street traffic.
   -  Observe and record vehicle queues; direction/distance.
   -  Place (if ADT is of interest) automatic recorders on selected
      road links for a weekday or more if necessary.
   -  If the office building contains a 24 hour operation, such as a
      computer facility, trip generation counts may be made at a
      similar local building between 6 to 9 AM and 4 to 7 PM to verify
      a local, more accurate trip rate per 1000 sq.ft. of gross
      building area.  Note: the survey building size and occupied
      space must be checked.
   -  If a signal warrant is to be checked the turning movement counts
      should be extended to 12 continuous hours.

                                   18



Complex Site Access Study For An Office Park

Included in the complex site access study are the same items
previously listed for a basic study (although more extensive in the
number and complexity of locations), as well as the following.

   -  Employee residence zip codes, for a nearby office building
      representative of the office park, would be obtained grouped by
      zip code and displayed on an area zip code map (i.e. percent
      distribution by zip code districts).  Employee trips would then
      be assigned by zip code to the study area road network.  This
      establishes a very realistic trip distribution pattern for the
      new office park.  Trips are then assigned to the networks based
      on knowledge of the travel patterns in the area.

   -  For projects which deal with 20 year traffic projections and the
      possibility of changing trip distribution patterns over the
      years, gravity model runs made by areawide agencies can be used. 
      Alternatively, the Quick Response System [3] or various software
      systems available commercially may be used with future areawide
      land use forecasts.

   -  Peak hour turning movement counts for complex studies may
      involve 10 to 20 intersections or ramp locations for which the
      data must ideally be recorded simultaneously.  Data tabulations
      frequently are computerized.

   -  The 10 to 20 year analyses usually involve rather complex
      solutions which require a firm understanding of as-built and
      future roadways.  Therefore construction plans, become extremely
      important to enable creative solutions to be developed.

   *  Tabulate Data: Calculate LOS

Newly collected data such as zip codes and trip generation rates, are
combined with other available data, as required to establish a data
base for technical analyses.  The second task in this phase,
calculation of the level of service, is very critical . The level of
service discussion is presented in Appendix C.
____________________

[3].  "Quick Response System (QRS) Software Documentation"; Federal
Highway Administration (HHP-22), January 1984. see also: Quick
Response Travel Estimation, (NCHRP 187), Transportation Research
Board, Washington DC, 1978.

                                   19



   *  Identify Site Access/Circulation Constraints And Opportunities

Having completed the technical analyses site access pros/cons should
be summarized in both written and graphic format.  The following
information should be included as applicable:

   -  Level of Service results for peak hours
   -  Peak hour queuing problems
   -  Right-of-way restrictions/availability
   -  Special site access opportunities or constraints based on the
      analyses of current peak hour conditions
   -  General information i.e., roadway lane configurations, average
      daily traffic trends for the past five years, etc.

PHASE II.   PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION WITHOUT SITE
            DEVELOPED

Phase II of the site access study process uses Phase I existing
traffic and estimates future peak hour traffic.  The projection
process then results in a new LOS estimation and other analyses to
identify future peak hour conditions without the site developed.

   *  Establish Past Growth Rate in Key Corridor(s)

Historical average daily traffic volume data, usually available from
state or regional agencies, is most often used to determine the three
to five year annual average rate of change ( e.g. " + 4% per year
increase in through traffic" ). Unusually high rates of change must be
carefully considered since such a rate may not be sustained over a
long period of time.  As areas reach maturity, corridor travel demand
tends to stabilize due to peak period congestion and upstream
bottlenecks; so growth rates in certain corridors may stabilize. 
Growth rates will vary by corridor.  Alternatively, existing and
future assignments from a regional planning agency can be used to
develop growth rates to be applied to existing traffic.

For the  basic site access study, the growth rate is not too critical  
an issue.  For a complex mid to long term study, this can be a very
critical technical issue for reasons described later in this section. 
Basically the issues are 1) the rate of increase for a complex study
occurs over an extended time period and 2) annual increases in traffic
"through" key study intersections are generated by new development
"beyond" the study area.  How far beyond, and to what extent annual
increases represent adjacent new development is usually an issue for

                                   20



discussion and resolution.

Once resolved annual rates are applied to existing peak hour volumes
to achieve 10 to 20 year traffic projections.  Care must be taken to
adjust intersection volumes when corridor growth rates differ within
the study area.

   *  Identify Changes In Road Network And Land Use Type/Density

These two items are not very critical in a basic site study.  For
example, the study area road network probably will not change too much
in six months or a year.  Nevertheless, changes must be considered
because street patterns can be changed, signal phasing altered and key
road links added, sometimes by another private developer.  Also a new
development nearby may influence the degree of change in level of
service along with changes in the subject site.  Once identified in a
basic study, a roadway or traffic operational change may mean that the
previously adjusted peak hour volumes must be re-adjusted to account
for changes in travel patterns etc.  Also, if the new land use is
considered to be significant, peak hour trips can be generated,
distributed and assigned to the road network.  The trip generation,
distribution and assignment process is described in Appendix C.

In the case of a complex site study with 10 or 20 year analyses,
changes in the road network and land development can become very
complex, as illustrated previously in Figures 4a, 4b and 4c.  Road
network assumptions at critical stages must be considered within a
subarea context by state, regional or local planners to the degree
necessary to complete a site access study, within its time and funding
constraints.  Land development changes are even more complex than the
road network changes due to economic and market uncertainties.  If a
large subject tract is to be rezoned, the issues can become even more
complex.  Nevertheless, through careful discussions reasonable
guidelines can be agreed upon to permit road networks and "new" land
use types, locations and densities to be selected.  After all, this is
a modeling process with the results allowing for alternatives to be
tested.  It is not a fixed process wherein a change cannot be
evaluated at a later date. This being the case, as illustrated in
Figures 4a, 4b and 4c three road networks and new land development
"densities" can be identified.

Referring back to annual growth rates, in a complex study there is
always concern about an issue called "double counting".  For example,
consider the following five step process:

                                   21



      Step 1:  Existing AM peak hour traffic volumes
                                 (times)
      Step 2:  An annual growth rate of 3.5% per year for 10 years
                                 (plus)
      Step 3:  Other "new" 10 year development trips generated
               distributed, assigned to the road network
                                 (plus)
      Step 4:  New subject site development trips generated,
               distributed, assigned to the road network
                                (equals)
      Step 5:  Total mid-term AM peak hour traffic volumes


   ³ Step ³    ³ Step ³    ³ Step ³     ³ Step ³    ³ Step ³

   ³  1  ³  +  ³  2  ³  +  ³   3  ³  +  ³  4  ³  =  ³  5  ³

      (Note that Step 4: Site Traffic was not included in Phase II; it
      is, nevertheless important at this time).


The issue is: does the +3.5% per year growth rate over compensate or
"double count" for other "new" development?  A comparison to areawide
20 year traffic projections may indicate that the areawide projections
are different.  Experience has usually indicated +1 to +2 percent
annual growth rates plus significant other "new" development results
in reasonable projections.  However, critics argue that this may not
be true in high growth areas!  A sensitivity analysis can be carried
out to determine the degree to which annual growth rates influence the
solutions or the share of the road improvements to be supported by the
subject site developer.

   *  Project Phase I Peak Hour Traffic To Future Study Year

For a basic study, this is a simple task which involves calculations
for a six month or one year period.  The trip generation trip
distribution and trip assignment processes are described in Appendix
C.

A complex study requires resolution of issues such as: staging
year(s), road network(s), annual growth rate(s), and other new
developments).  Then the calculations are performed to achieve
projected AM/PM peak hour traffic.  Obviously, factors can be used to
convert peak hour traffic to average daily traffic in any year, if
this information is considered important.

   *  Calculate Level of Service

The Highway Capacity Manual and/or other publications are used to
determine the peak hour level of service without the subject site
developed (See Appendix C).

                                   22



   * Identify Changes Between Existing And Future Situation

The following level of service comparison is now possible for a basic
study:

                                 Phase I            Phase II
        Intersection            Existing             Future
             No.            Level of Service    Level of Service

                             (AM)    (PM)          (AM)   (PM)
              1                A       C             B      C
              2                A       D             A      D
              3                B       D             D      F


For a complex study, this information would be available for each
staging period (5, 10 and 20 years) in comparison to the existing
situation.  The results are used to identify locations which are
congested   in excess of Level of Service D in urban areas or Level of
Service C in rural areas, without the subject site developed. 
Comments can vary depending on the results:

   -  Were the road networks properly selected?
   -  Were the annual growth rates sufficient or excessive?
   -  How bad is the level of service, as compared to the desired
      level of service, and what is causing it?
      Were the other "new" developments properly selected and located?

Regardless, Phase II provides an excellent representation of future
conditions without the subject site developed.  Besides level of
service comparisons by intersections certain technical issues are
quite evident:

   -  Geometric design adequacies/inadequacies become apparent.
   -  Site access opportunities or constraints can be identified.

PHASE III.  PROJECT PEAK HOUR SITE DEVELOPMENT TRAFFIC

Technical guidelines associated with the performance of Phase III
tasks are described in this section.  Certain aspects of the trip
generation, distribution and assignment process are discussed in
Appendix C.

Select And Apply Appropriate Trip generation Rates

This step estimates the site generated peak hour trips and is the same
as described in Appendix C.

                                   23



   *  Determine Trip Distribution pattern And Assign Trips To Road
      Network

Having estimated the Bite generated peak hour trips, it must be
determined to what degree the trips Will use the study area road
network.  The trip distribution and assignment procedures are
described in Appendix C.

The Phase III analyses result in Bite related peak hour traffic
assignments which are combined with Phase II results.

PHASE IV.   PROJECT FUTURE PEAK HOUR TRAFFIC SITUATION WITH SITE
            DEVELOPED

Phase IV of the site access study process establishes the peak hour
situation with the site fully developed and occupied.  Phase IV is
based on the Phase II and Phase III results.  The steps for conducting
Phase IV are as follows.

   *  Combing Phase II Background Traffic With Phase III Assigned
      Traffic To Achieve Total Peak Hour Traffic

AM and PM peak hour network assigned traffic volumes for Phase II
(without the subject site developed) are combined with Phase III AM
and PM peak hour volumes (subject site generated trips) to achieve
total peak hour traffic volume networks with the site developed.

For a basic study, where the road network does not changer this is a
simple additive process.  For a complex study, where the road network
may change with the site developed additional network assignments may
be necessary to represent conditions with the site developed. 
Depending upon the circumstances,, if as-zoned site development
conditions are to be analyzed too, then a different set of road
networks may apply because additional road improvements may be offered
with the proposed development.

   *  Calculating LOS:  And Compare To Phase I And Phase II LQS
      Results

Having combined the Phase II and Phase III peak hour volumes, Phase IV
level of service is calculated for key intersections and ramps using
the Highway Capacity Manual, and/or other publications.

                                   24



   *  Identify Changes Between Phase I, Phase II And Phase IV Results

Level of service can now be summarized as indicated below for a basic
site access study:

                AM PEAK HOUR LEVEL OF SERVICE COMPARISON

                                Future Situation     Future
                     Existing     Without Site      With Site
   Intersection      Situation      Developed       Developed
        No.          (Phase V      (Phase II)      (Phase III)

         1               A              B               C
         2               A              A               C
         3               B              D               E

These example level of service comparisons indicate that if LOS D was
the acceptable LOS criteria the LOS E would indicate a location which
would operate in excess of an acceptable LOS as a result of the site
being developed.  This one level change in operating efficiency may be
improved to a LOS D through further evaluation of intersection
geometrics, signal timing/phasing or other improvements.

For a more complex multi-year study, the results would be compared on
a similar basis, except that the analysis would consider each stage of
development until build out occurs.

To illustrate a complex alternative, consider one intersection for a
site being studied for as-zoned and as-proposed conditions (as-zoned
refers to the current zoning, whereas as-proposed refers to the zoning
requested by the developer).  Figure 5 illustrates the AM peak hour
levels of service comparison for the intersection.

While the results are rather simpler and meaningful, there are very
complex implications associated with the findings that can only be
understood through very careful review of the analyses.  For
intersection 1, as with as many as 10 or more key locations studied,
the following can be inferred.

   *  In the short term, assuming that a LOS D is acceptable the
      intersection operates satisfactorily with or without the site
      developed either as-zoned or as-proposed.  Note however that the
      LOS C without the site developed deteriorates to a LOS D for as-
      zoned conditions, but improves to a LOS C for as proposed
      conditions.  This "improved" LOS with the as proposed option
      could be a function of several factors.

                                   25



                                FIGURE 5
       AM PEAK HOUR LEVEL OF SERVICE COMPARISON FOR INTERSECTION 1

                             AM PEAK             ROAD NETWORK
       CONDITION             LOS [1]             CONFIGURATION
  ------------------         -------      ---------------------------
  Existing Situation            A                      1


                     Short Term Conditions (+5 Yrs)

Without Site Developed          C        2 (1 + committed/planned +
                                         5 year improvements)

  With Site Developed           D        2 + as-zoned improvements
       As-Zoned

  With Site Developed           C        2 + as-proposed improvements
      As-Proposed


                  Mid Term Conditions (+10 yrs)

Without Site Developed          D        3 (2 + committed/planned +
                                         10 year improvements)

  With Site Developed           E        3 + as-zoned improvements
       As-Zoned

  With Site Developed           D        3 + as-proposed improvements
      As-Proposed


                     Long Term Conditions (+20 yrs)

Without site Developed          F        4 (3 + committed/planned +
                                         20 year improvements)

  With Site Developed           F        4+ as-zoned improvements
       As-Zoned

  With Site Developed           E        4+ as-proposed improvements
      As-Proposed

  [1]  AM Peak Hour Level-of-Service at Intersection 1

                                   26



   -  the as-proposed density may generate fewer AM peak hour trips
      than the as-zoned density, so assuming the road network is
      essentially the same for both the as-zoned and as-proposed, the
      LOS would obviously improve.
   -  the as-proposed road network may be significantly more efficient
      or improved as compared to the as-zoned road network even though
      the trips generated in each option are similar.  This would also
      improve intersection level of service.

   *  In the mid-term, LOS D is achieved without the site developed. 
      With the site developed as-zoned, a LOS E is achieved which may
      mean that public funds are necessary to reduce the LOS E to a
      LOS D or better.  With the site developed as-proposed, a LOS D
      is achieved.  This level of service is achieved primarily by the
      roadway improvements proposed by the site developer.

   *  In the longterm with or without the site developed as-zoned, a
      LOS F is achieved making public expenditures necessary to
      correct the situation.  With the site developed as-proposed a
      LOS E is achieved prolonging the point at which the need for
      public expenditures would occur.  A LOS D may be achievable but
      very significant additional roadway improvements may be
      necessary which may not be economically feasible.


PHASE V. DEVELOP SITE ACCESS RELATED SOLUTIONS

Phase V of the site access study process is the creative phase which
identifies site access related improvements which the developer agrees
to construct.  This phase consists of two major tasks as described
below.

   *  Evaluate Alternative Solution To Achieve Acceptable Levels Of
      Service

Having completed the level of service peak hour comparisons, an
assessment should be made of the need to incorporate changes in land
use or transportation improvements including TSM actions, assuming
Phase IV results were accurately analyzed.

For a basic site access study, the evaluation process is not too
difficult because of the limited number of alternatives.  Typical
changes which could be considered are:

   -  Reassessment of trip generation rates or the trip distribution
      pattern.
   -  Consideration of TSM actions to reduce peak hour traffic and
      improve level of service.

                                   27



   -  Consideration of modifications to key intersections or road
      links to include widening signal timing/phasing changes,
      channelization modifications, changes in ingress/ egress points,
      or the number of entrances, additional lanes, etc.  Other
      factors such as access related improvement costs, ease of
      implementation, possible citizen reaction acceptability to
      state/local officials, level of service improvement etc., should
      also be considered.  In some instances re-analysis is necessary
      to evaluate the pros/cons of alternatives.  Occasionally, a
      significant change in land use type or density may be necessary.

For a complex site access study, the evaluation process is far more
extensive because of the greater number of factors which can influence
the results.  For example, typical changes, in addition to those
described for a basic study, may include the following.

   -  Significantly different new land use development programs.
   -  Significantly modified road networks to include flyovers,
      tunnels, etc. to alter the access situation.  Preliminary design
      studies may be considered necessary to evaluate possible
      solutions.
   -  Implementation of major TSM programs to significantly influence
      site generated traffic volumes by changing travel
      characteristics.

These changes may constitute rather extensive changes in the technical
analyses performed.  It should be noted that such a major re-
evaluation should only be considered after a review of long term LOS
results.  In other words, Phases II, III and IV in a major study may
only involve a 20 year PM peak hour projection and LOS evaluation at
selected locations.  If the results are unacceptable, then a major re-
evaluation is performed -- or even a "reverse" analysis is performed
to identify alternative land use options that can be supported by the
road network.  Then, after the major re-evaluation, Phases II, III and
IV are considered for short term and mid-term analyses.

   *  Select Preferred Solution:  Document Findings

Having completed the site access analyses, the pros/cons of various
alternatives and the preferred solution should be discussed with the
project team.  Coordination with on-site circulation details, should
be considered.  Technical modifications may be necessary to make the
off-site access improvements compatible with on-site circulation
improvements to

                                   28



include parking facility (lots, decks, garage) access points. once
this is accomplished, then the final site access study findings can be
documented in written and graphic format.

This phase constitutes the principal technical analyses associated
with the preparation of a site access study.  The remaining phases
depend upon the original purpose of the study.  Since most site access
studies proceed with local review and either approval or disapproval
for the proposed action, this is the context within which the two
remaining phases are described.


PHASE VI.   NEGOTIATE SITE ACCESS

Phase VI of the site access study process is necessary since the
solutions may change after consultations with the local officials. 
Further analyses may be necessary.  The two tasks in Phase VI are as
follows.

   *  Negotiations Between Local Officials And Developers To Reach
      Agreement On The Proposed Development

Following distribution of the site access study findings presentations
and/or workshop meetings should be held to explain technical aspects
of the study.  Since the issues can become quite complex for
explanation and discussion within normal meeting times, every effort
should be made to use effective audio-visual techniques to clarify
issues and focus the discussion.  The review process is usually
subject to local and state regulations.  Technical issues may be
raised regarding  (1)  analyses which were not performed, (2) 
techniques used in the technical analysis process and (3)  assumptions
concerning trip generation rates, etc. used in the process.

   *  Supplemental Technical Analyses To Resolve Outstanding Issues

The type and extent of supplemental analyses depends upon the issues
raised.  Occasionally, technical site access related differences are   
simply negotiated.  Land use, utilities, height, or other issues    
constitute the remaining items for resolution.  When site access
remains an issue, it may involve discussions regarding one or several
of the following issues:

   -  Proposed land use/density is not acceptable to the local
      planning staff.
   -  Trip generation rates are unreasonable or do not conform to
      local rates.
   -  Trip distribution patterns/changes over time are not properly
      documented.

                                   29



   -  The LOS calculations are either incorrect or the locally
      preferred technique was not used or properly interpreted.
   -  TSM actions were not used to the extent deemed necessary or
      assumed effectiveness of TSM actions were too optimistic.
   -  Private share of improvements (costs) are not sufficient.
   -  Site plan details regarding building size/location, parking faci
      lity operations and pedestrian improvements are unacceptable.

Appropriate technical analyses must then be performed to resolve these
issues.


PHASE VII.  IMPLEMENT PROJECT/ACCESS IMPROVEMENTS

Phase VII of the site access study process occurs after agreement
between the developers and the local officials is reached.  Tasks that
may be required in Phase VII are as follows:

   *  Assist Site Engineer In Preparing Construction Plans

Assist the developer, site engineer, and architect in the preparation
of final site plans and construction plans for roadways, parking
facilities and traffic operational measures to aid implementation.  A
coordinated effort is necessary to ensure that both public and private
access improvements are implemented on a timely basis especially for
projects to be constructed over 10-20 years, On-site circulation
improvements are also carefully coordinated with building/entrance
locations, as well as parking facilities,i.e. lots, decks, garage, to
ensure on-site efficiency and interface with the off-site local road
network.

   *  Develop Signalization Plans/Specifications (If Applicable) For
      Bid

If new or modified signalization is required plans and specifications
can be prepared for bid.  This ensures that the plans are coordinated
with publicly funded improvements or existing traffic operational and
roadway features.  Since the project developer occasionally pays for
all or a portion of new signal installations this responsibility for
development of plans and specifications can be considered appropriate
by local agencies.

                                   30



   *  Privately Funded Roadway Or Traffic Operational Improvements
      Implemented

The final step of the site access study process is implementing the
physical site access related improvements which may encompass roadway
or traffic operational changes, fully or partially funded by the site
developer.  For basic site access studies, this may involve the
following improvements often funded totally by the developer:
   -  An additional right turn deceleration lane at a key intersection
      to improve peak hour efficiency.
   -  Modification to a traffic signal installation.
   -  Site plan modifications to improve entranceway ingress/ egress
      efficiency.

For complex site access studies, the previously mentioned improvements
are typical of projects totally funded by the developer, while the
following, more expensive improvements are typical of those usually
partially or fully funded by the developer.

   -  Construction of significant multi-lane roadway sections
      connecting major or minor arterials.
   -  Construction of additional lanes to widen major roadway
      corridors.
   -  Installation of traffic signals, including interconnection
      cable.
   -  Construction of flyovers or tunnels to improve peak hour traffic
      conditions.
   -  Construction of a complete or partial interchange.

These facilities are built to public agency standards with future
maintenance usually funded by public agencies.  It should also be
noted that non-highway related improvements or actions are sometimes
funded, e.g. ridesharing programs or shuttle bus service.

                                   31



                 [ This page intentionally left blank ]

                                   32



IV, CONCLUSIONS

The site access study process, as described phase by phase for both
basic and complex studies, is a widely used technique for resolving    
land use and transportation issues.  With the increasing emphasis on
shared public and private participation in transportation and TSM type
improvements it is clear that the technique is also an important
element in the investment decision-making process of the developer.

This places a great deal of responsibility on not only the developer
but on the agency or person(s) responsible for the negotiations.  It
also requires that the technical process be more widely understood and
technically sufficient to provide meaningful results within available
budget and time constraints.

The general process described in this handbook has been used for some
time.  However, its importance in the transportation planning process
and its impact on certain local, sub area and regional planning
decisions has sometimes been overlooked.  Due to the wide range of
issues involved in site access studies it is difficult to offer more
than general guidelines in a handbook of this type.  Attempts to
overcome this have been made by presenting four case studies in
Appendix D. This does not, however, address all problems and
situations that may arise.

Complicating the situation further is the fact that issue
identification alone is difficult.  For example, a project may appear
to have no access problem, but through a series of events or
oversights very serious access issues may arise.  The access issues
may become more complicated due to citizen opposition, site
constraints which influence on-site circulation, or parking facilities
or other technical elements.  And of course, the negotiation process
and implementation stages may introduce new issues for technical
resolution.

Besides recognizing the importance of the site access study process,
it is also important to realize that certain technical factors in the
process can significantly influence not only the level of service
results but the entire site plan land use type/density and related
roadway and traffic operational improvements, including TSM actions. 
One of the most important elements is the trip generation rates which
were specifically evaluated through case studies for level of service
sensitivity in this handbook.

Of course, other elements of the study process such as the number of
gross square feet per (office) employee, mode of arrival (percentage),
vehicle occupancy and trip distribution

                                   33



patterns can also individually or in combination affect level of
service and other study findings.

In view of the technical complications associated with site access
studies, the guidelines identified in this handbook should be modified
to coincide with local or state ordinances and approved policies.

SUMMARY OF CASE STUDIES

The site access study process described in the previous chapters was
used to conduct four case studies.  The principal reason for
performing the case studies is to show the application of trip
generation rates and to illustrate how peak hour level of service is
influenced by a change in trip generation rates.  A secondary purpose
was to illustrate the sensitivity of other variables to the peak hour
levels of service.  The four case studies are described in Appendix D.
The results are summarized below.

   *  Variation In Trip Generation Rates

Case Study No. 1, a basic site access study, indicated that the key
study intersection was significantly improved from a LOS F to LOS E by
a 25% reduction in the office and motel trip rates.  At other less
heavily traveled intersections, this same reduction in trip rates did
not change the levels of service

Case Study No. 2, a basic site access study, indicated that a 10%
increase or a 10% decrease in trip generation rates did not change the
levels of service or level of efficiency at any intersection studied.

Case Study No. 3, a complex site access study, indicated that with an
increase in trip generation rates from the actual study rates to the
updated NCHRP 187 or ITE rates, the levels of service at all five
intersections were reduced significantly.

Case Study No. 4, a complex site access study, used a wide range of
trip generation rates, influenced by a change in other key factors. it
indicated that the most heavily traveled intersection was influenced
by one level of service, either better (LOS E to LOS D) or worse (LOS
D to LOS E), by the various changes in trip rates.  The less critical
intersections were influenced by the rates but the levels of service
never became worse than LOS D. Changes in mode of auto arrival (an
increase from 81% to 90%), auto occupancy (a reduction from 1.25 to
1.1) and arrival / departure rates (an increase from 55%/50% to
65%/60%) resulted in less efficient peak hour operating

                                   34



conditions by one level of service.

   *  Variation In Trip Distribution Patterns

Case Study No. 1, Condition 3, indicated that a reduction from 75% to
55% in the site trips distributed through a key intersection did not
change the level of service at the key intersection, but it was
sufficient to change a LOS E to LOS Dr a range of 90 units at the
second most important intersection.

   *  Variation In Normal Growth Rate

Case Study No. 1, Condition 4, indicated that a reduction in normal
annual growth rates on the major corridor - and a lesser reduction in
mall site traffic - produced a very much improved level of service at
the key intersection from a LOS F or LOS E in the PM peak hour for
three conditions to a LOS B/C in the PM peak hour for Condition 4.

While the case studies do not illustrate a direct relationship between
a change in trip rates and level of service, it should be apparent
that the rates can seriously influence the results.

                                   35





                               APPENDIX A
               DEFINITIONS: SITE ACCESS STUDY TERMINOLOGY

The following definitions are presented to clarify the technical
terminology associated with site access study analyses.

Capture Rates for Pass-by Traffic:
   Proportion of trips attracted to the development from traffic
   normally passing-by the site.

"Committed" Development:
   New land use projects for which site location, type and density are
   firmly established for construction.

Committed Roadway/Traffic Operational Improvements:
   New roadway or traffic operational improvements for which plans are
   firmly established and funded, for construction.

Existing Zoning:
   When applicable by local ordinance the currently approved land use
   type and density by Floor Area Ratio (FAR) which could be built on
   the subject site by right.

Internal" Trips:
   Site generated trips which occur between two or more land uses
   located on the subject site with both trip ends on-site.

Level of Service (LOS):
   A set of criteria that describes the degree to which an
   intersection? roadway, weaving section or ramp efficiently serves
   peak hour and/or daily traffic.  LOS definitions are presented in
   Appendix C.

Metropolitan Planning Organization (MPO):
   An agency responsible for regional (metropolitan) planning
   functions including transportation, and land use as it relates to
   member jurisdictions.

Mode Split:
   The percentage split of site generated trips which utilize various
   modes of travel to access a site, i.e.  auto, bus, subway, walk,
   bicycle, etc.; with the extent of use depending upon the degree to
   which the service or facility is available.

Normal Growth Rates:
   The annual rate of, change in through traffic on principal off-site
   roadways as determined using historical 24 hour average daily
   traffic volumes.

"Normal" Site Access Study Process:
   Site access related analyses initially performed with fixed, or a
   certain number of

                                   A-1



   land use types/densities for which selected site access
   improvements are developed to serve the preferred land use.


"Off-Site" Access:
   The road network beyond the site's boundary which provides
   vehicular site access.

"On-Site" Circulation:
   Vehicular network which primarily accommodates site generated
   traffic within the site boundary and includes not only roadways,
   but parking lots, decks, and garage travelways.

"Planned" Development:
   New land use projects for which site plans are being or have been
   developed, but no firm date has been set for construction. 
   Completion is expected within the study period.

"Planned" Roadway/Traffic Operational Improvements:
   New roadway or traffic operational improvements for which plans are
   being or have been developed but no firm date has been set for
   construction.  Completion however, is expected within the study
   period.

Project Staging:
   The time period, (years), when selected land use densities will be
   occupied therefore generating site traffic.  Staging years may, as
   an alternative be selected on the basis of the road network to be
   studied rather than selected on the basis of land use densities.

Proposed Zoning:
   The land use type and density proposed to be developed which
   necessitates re-zoning (when applicable) the land from the as-zoned
   condition; also described by Floor Area Ratio (FAR).

"Reverse" Site Access Study Process:
   Site access analyses performed with a fixed, or a certain number of
   road networks selected, to determine the range of land use
   types/densities which can be served by the preferred road network.

Roadway Capacity:
   The maximum number of vehicles which can pass a given point during
   a specified time period under prevailing roadway and traffic
   conditions.

Signal Warrant:
   The Manual on Uniform Traffic Control Devices for Streets and
   Highways prepared by the U.S.  Department of Transportation (1978)
   presents requirements (warrants) that should be met for a traffic
   signal to be installed.

Study Area:
   The road network and land area which encompasses

                                   A-2



   the principal intersection, road links, ramps, etc.  and new land
   use developments of primary concern in a site access study.

Trip:
   A single or one - direction vehicular trip with either the origin
   (outbound) or destination (inbound) or both inside the study area. 
   Each trip has two trip ends.

Trip Assignment:
   After applying the geographic corridor percentage total peak hour
   generated trips, the resulting corridor trips are assigned to the
   study area road network.  The process is repeated for inbound (to)
   and outbound (from) site trips for each land use type.

Trip Chaining:
   A single one directional vehicular trip with intermediate stops. 
   For example an AM peak hour vehicle (trip) originating at a
   residence would stop at a retail convenience store, then proceed to
   work at an office site.  Reverse trip chaining may occur during the
   return PM peak hour trip.  Various other trip chaining combinations
   may occur which tend to complicate trip purpose and trip
   generation.

Trip Distribution:
   The geographic distribution of trip ends attracted to the site,
   usually expressed as a percentage of the total site trips generated
   via (and assignable to) major site access corridors.

Trip Ends:
   The total of all trips entering plus all trips leaving a specific
   land use within a specific time period.

Trip Generation Rate:
   The ratio of total trips or trip ends generated (from the site) or
   attracted (to the site) during a specific time period, per some
   measure of related land use activity such as trips per room (hotel)
   trips per 1000 gross square feet (office space)

                                   A-3





                               APPENDIX B
                ISSUES AND TRENDS IN SITE ACCESS STUDIES

A site access study describes how traffic generated by either new land
use(s) or replacement land use(s) will be served by an existing or
future road network.  This Appendix presents the reasons for
conducting a site access study and discusses the major issues and
emerging trends in site access studies.

ISSUES - SITE ACCESS STUDIES

A private developer commissions a site access study in order to
satisfy either his own needs or to fulfill public agency requirements,
or for both reasons.  The study is usually performed to meet one of
the following technical needs.

   1) To obtain agency approval to re-zone a specific tract of land;
      from a residential density to an office density for example.

   2) To obtain site plan approval for development of a tract as-
      zoned.

   3) To obtain approval of a special exception in land use or the
      site plan; for example adding a convenience retail counter to an
      existing service station.

   4) To aid in negotiations for the acquisition of right-of-way by
      the public agency responsible for roadway improvements, i.e. for
      widening a roadway in front of a shopping center, which would
      significantly change vehicular access patterns and reduce the
      number of retail parking spaces.

   5) To aid in the resolution of different opinions regarding
      possible land use development options.  For example, a public
      agency may consider that a tract can only be developed as a
      single family residential use whereas a developer may consider
      townhouse offices a reasonable alternative.  A site access study
      will be used to compare the critical issues with the matter
      resolved with or without court action.

In the previous cases, the proposed land use density is given, whereas
in the following instances, land use options vary.

   6) To aid a developer in evaluating potential development benefits
      and costs in advance of the actual purchase of a specific tract
      of land.  If the tract is not developed

                                   B-1



      practical land use mixes, associated road networks and road
      costs will be identified by performing a site access study for
      the developer.  If the tract is already developed re-use options
      will be evaluated and similar findings developed.  Usually,
      selected land uses densities are tested for roadway network
      implications.  If a reasonable land use density is considered to
      be achievable a firm option or actual purchase of the tract will
      occur, Then, if appropriate, a rezoning study will be instituted
      with a more refined site access study being performed for the
      preferred development plan,

      For very unusual tracts, which are almost inaccessible a reverse
      process can be used by holding the future road network constant
      and determining the land use(s) density which can be efficiently
      accommodated on the subject tract.

The last example of a need for a site access study occurs when a site
plan is being developed with the land use fixed, but with variable
building shapes and locations on the site plans.

   7) Recognizing that there is a relationship between "on-site"
      circulation patterns (within parking lots, decks or garages) and
      entrances to the "off-site" road network, a site access study is
      occasionally necessary to aid in the resolution of "on-site"
      issues related to parking facilities.

With an increasing awareness by developers of parking costs for decks
and garages, and the need to have efficient ingress/egress for
competitive market conditions, "on-site" circulation issues are more
frequently being studied in combination with the site access study,
Sometimes "off-site" access can be enhanced by changes in "on-site"
circulation,

TRENDS - SITE ACCESS STUDIES

While site access studies have been important in the past, there are
three reasons why such studies will be even more critical in the
future,

First, the economic situation has changed significantly throughout the
United States with respect-to the ability of public agencies to fund
major roadway improvements.  An obvious source of funds to aid public
agencies in the construction of major roadway improvements is for the
developer of sizable commercial tracts to build a portion of a roadway
or to contribute to a fund for future road improvements.  Site access

                                   B-2



studies are necessary to quantify the nature and extent of road
improvements to ensure that reasonable and effective roadway
improvements are made.  Such studies also enable cost sharing to be
more accurately discussed which expedites negotiations and
implementation.  For example, the site access study process can be
used to define the pro-rata share of a road improvement cost between
two private developers in terms of traffic generated by each
developer's tract.  The studies also allow incentives to be tested in
case additional density is to be allowed for additional privately
funded road improvements.  Examples of the benefits of this emerging
process have been well documented so the trend is real and the results
are actually being realized.  To what degree the process will be
intensified or expanded depends on a variety of factors - one of which
is a well conceived and documented site access study.  When
effectively implemented such a program could have significant benefits
in reducing public agency road costs.

Secondly, we are midway in the 1980's (1985), through a decade long
evolutionary change in real estate finance.  Real estate is evolving
into a mature investment medium that is approaching equal footing with
stocks and bonds.  Through the 80's the real estate lending community
will become much more integrated, with the roles of individual types
of institutions blurring.  This is also leading to major universities
instituting real estate schools to better prepare graduates for far
more complex financial issues in land development than have previously
existed.  Since location and accessibility are so important to
successful development projects the ability of the site access study
process to aid in the resolution of complex issues is especially
critical.

Thirdly, while the real estate revolution in the 80's has been in
finance, significant changes have also occurred in various land uses. 
Trends have become apparent in the last five years and will continue
to be forced in the marketplace through the latter 80's.

Table B-1 summarizes the major market shifts.  Site access studies are
applicable to most of the items as discussed below:

   Item 1:  With increasing concern about building quality, design and
   amenities there is a greater awareness of accessibility,
   particularly if developers must pay for significant roadway
   improvements.
____________________

[5]  "Emerging Trends in Real Estate:1985"; Real Estate Research
Corporation; November 1984 for Balcor/American Express, Inc. [6].
Ibid.

                                   B-3



                                TABLE B-1
                        MARKET SHIFTS IN THE 80's

The real estate revolution of this decade is in finance, which has
been amply described earlier in this Appendix.  However, changes are
also occurring in various land uses, as summarized below. All of these
trends have become apparent in the last five years and will continue
to be forces in the marketplace through the latter 80's.

   1.  A pronounced upgrading in construction quality for all types
       of buildings and increased focus on both design and amenities.

   2.  Greater energy efficiency in new and retrofitted buildings.

   3.  Mixed-use developments becoming more the rule than the
       exception.

   4.  Dramatic rise in rehabilitation, spurred by tax incentives and
       changing consumer tastes.

   5.  Revitalization of one downtown after another, generally led by
       big-city examples but extended now to small cities across the
       county.

   6.  Blurring of office and industrial land use categories,
       typified by the rise of business parks.

   7.  Introduction of so-called "smart" office buildings, providing
       sophisticated control and monitoring of energy utilization,
       safety, telecommunications and maintenance systems. (By 1990,
       many office buildings will be "geniuses".)

   8.  Real estate time-sharing coming of age, with 75,000 to 100,000
       new buyers a year.

   9.  Rapid expansion of all-suite hotels, probably to the point of
       market saturation.

   10. Major hotel chains creating spinoffs to penetrate both higher-
       and lower-end markets; here, success will be mixed.

                                   B-4



                          TABLE B-1, Continued

   11. Proliferation of specialty and festival retail centers, once
       again starting in larger cities and moving rapidly into
       second-tier markets.

   12. Continued focus on off-price retailing, with success tempered
       by countermoves on the part of traditional retailers.

   13. Downsizing of new housing units in response to affordability
       problems and changes in household characteristics.

   14. Condominiums capturing a bigger share of the residential pie.

   15. Renewed developer and investor interest in market-rate
       multifamily rental housing.

SOURCE:   Emerging Trends in Real Estate: 1985
          Real Estate Research Corporation, November 1984 for
          Balcor/American Express Inc.

                                   B-5



Item 3: Mixed use developments are being more frequently considered in
site access studies, with a wide range of land uses and densities, as
well as shared parking possibilities and on-site (or internal trip
making between on-site land uses).  Such site access studies must be
carefully performed to fully understand critical issues.  Very little
data are available to recommend a method for estimating reduced
driveway volumes because of combined uses.[7]  This means that trip
generation rates for mixed use developments must be carefully
considered.  And, of course, a number of other technical elements are
of similar complexity because historical data are not available. 
Developers of mixed use projects frequently contribute to the funding
of public roadway improvements.

Item 4: A dramatic rise in rehabilitation raises complex site access
study issues because existing land uses are being upgraded; replacing
existing traffic volumes with traffic generated by new uses and
sometimes density changes.  Private contributions for new roadway
improvements are not as easily negotiated in this case because the re-
use may be allowed under current zoning.

Item 5: Revitalization in downtown sectors co-mingles site access,
parking and, when applicable transit issues making it necessary to
study not only site access but parking demand and alternative modes of
travel.

Item 6: Industrial space is more frequently being used for general
office space, making the trip generation rates for office space and
industrial space more equal.  In the past, industrial space was more
predominantly related to warehousing and storage so the generated
trips were significantly lower than for general office space.  This
change is occurring due to increase in business parks and competitive
market conditions.  This variation in trip rates is frequently an
issue in site access studies.  The industrial space with office uses
can be compared to a multi-tenant office building.  However? a single
tenant office building has different characteristics such as higher
square feet per employee.  Further, corporate policy can be used to
maximize the use of ridesharing and TSM actions to reduce peak hour
traffic without creating marketing problems associated with a multi-
tenant office building.
____________________

   7. Buttker Carl H. Using the ITE Trip Generation Report July 1984
      pp 14.

                                   B-6



Item 7: Telecommunications and 24 hour computer operations in office
buildings will influence (reduce) the number of peak period generated
vehicular trips and trip making characteristics.

Item 10: Hotel chains have created new market facilities with all
suites and no on-site restaurants or meeting room facilities.  This
could influence the number and type of generated vehicular trips,
which is an essential ingredient of site access studies.  These uses
generate moderate traffic volumes during the peak hours and require
site access studies less frequently.  Such studies are associated with
on-site circulation, parking facility needs or shared parking with
nearby office buildings.

Item 11: Specialty retail (often waterfront) centers require careful
consideration since the combination of retail uses can complicate site
access study analyses.  For example sporting (exercise, athletic)
clubs are being integrated into office buildings.  Children's day care
centers, which are usually developed on isolated tracts, are being
integrated with retail centers and office complexes.  Service stations
with maintenance bays are being converted to self service gas and go
with computerized payment.  Drive-in banks co-exist with the bank
building or are located within retail centers or building complexes. 
Fast food restaurants are incorporating drive-in windows and breakfast
openings which coincide with AM peak hour highway traffic conditions.

Item 12: Off-price retailing or outlet malls raise trip generation
issues because very little data are available for this new retail use. 
New traffic studies are necessary to understand trip making
characteristics.

Item 14: Besides residential condominiums, office condominiums are
more frequently being constructed.  The trip making characteristics
for this new use are not fully understood and yet this use is
frequently involved in site access studies.  Developers of residential
uses usually provide basic roadway infrastructure but cannot afford to
provide major roadway improvements such as flyovers, interchanges etc.
to the degree commercial or retail developers can.

In addition there is a growing concern that the public planning
process seems unable to cope with suburban growth and resultant
traffic congestion.  Possibly more effective solutions can be achieved
through greater private sector involvement and public-private
cooperation, which can be illustrated by:

                                   B-7



   -  Negotiated ad hoc agreements with private developers.

   -  Regulatory requirements for developer/employee involvement, such
      as the Los Angeles parking ordinances and the Placer County
      ordinance.

   -  Private sector led strategic planning and lobbying such as
      Houston's Mobility Plan and Dallas' Transportation Task Force,
      Los Angeles' Coalition for Rapid Transit, Californians For
      Better Transportation and the Tysons Transportation Association
      in Fairfax County, Virginia.

   -  Mechanisms to facilitate cooperation among private groups such
      as transportation management associations and employers'
      associations. [8]

In summary, emerging trends are being considered in current site
access studies, but with more 'hybrid' land uses and development
concepts comes the need for improved public-private negotiations. 
This requires more carefully conceived site access studies and updated
daily and peak hour trip generation rates for new and frequently used
land uses.
____________________

   8. "Mobility for major Metropolitan Growth Centers: A New Challenge
      for Private-Public Cooperation"; workshop conference, Los
      Angeles, CA; November 29-30, 1984

                                   B-8



                               APPENDIX C
TECHNICAL BACKGROUND

This Appendix describes trip generation, trip distribution/assignment
and level of service estimation procedures.  The procedures noted
herein are not all inclusive and locally acceptable procedures should
be used where applicable.

TRIP GENERATION

There are five steps to consider for selecting a trip generation rate,
and the final decision will be a function of the proposed land use
project and its complexity.

For example, for a basic study which involves 25 new townhouse office
units, consider the following steps.

Step 1: Check for available local trip generation rates, i.e.
      vehicular trips per unit per day, per AM and PM peak
      hour; inbound and outbound for a comparable site. Note
      that townhouse office tenants may vary significantly
      from project to project which may result in a wide range
      of trip rates since the occupants were so dissimilar.

Step 2:  Check the updated NCHRP 187 rates for an applicable range in
         trip rates. [9]

Step 3:  Check the ITE trip rates. [10,11]

Step 4:  Develop a special trip rate if local rates are not available
         by surveying a comparable townhouse office project for peak
         hour and daily traffic volumes on a typical weekday.

Step 5:  Select the most appropriate trip rates and apply to the 25
         units proposed to achieve total plus in and out site trips to
         be generated on a peak hour and daily basis. Since a
         townhouse office tenant mix may vary, provide for a possible
         range in trips generated.  If a variation may influence the
         results, it should be tested.

____________________

    9.   Development And Application Of Trip Generation Rates, Federal
         Highway Administration (HHP-22), January 1985
   10.   Buttke, Carl H., Using the ITE Trip Generation Report,
         Institute of Transportation Engineers, July 1984
   11.   Trip Generation, An Informational Report, ITE, Washington
         D.C., 1982

                                   C-1



For a complex office development to be built over 15 to 20 years,
another alternative is suggested since updated NCHRP 187 and ITE
office trip rates do not always account for a variation in TSM
actions, which influence the rates.  This technique as described
below, provides an excellent basis for understanding the rates and how
they may change due to certain development criteria; or changes due to
a variety of other factors, especially over a 15 to 20 year period. 
For non-office land uses, one of the five steps listed for a basic
study should be used.

Table C-1 illustrates the technique applied to an office building
containing 62,000 gross square feet of proposed office space.

Step 1:  Obtain the gross floor area (square feet) from the developer
         or architect.

Step 2:  Request from the developer or architect an estimate of the
         number of gross square feet per employee.  This may range
         from 200 in a pure governmental office building to 275 to 325
         in a corporate headquarter's building.  It may also vary as
         to whether the space is to be leased or owned by a company. 
         Companies generally make far more efficient use of leased
         than of owned space.  This is particularly true for corporate
         headquarters, which tend to have 275 square feet per employee
         in their own building and 200 to 220 in rented space.[121 If
         the user is not sure of the square feet per employee, then
         sensitivity tests can be conducted to determine the impact of
         this variable.

Step 3:  Divide the gross square feet (62,000) by the gross square
         feet per employee (275) to obtain the total number of
         employees (225).

Step 4:  Determine the mode of arrival, as a percentage of the total
         arrivals for employees traveling to the building.  Such
         information may be available from other nearby studies or a
         special survey, but most typically this is an experienced
         judgment item.  Note that the mode of arrival may change
         significantly over time due to new modes of travel being
         available or movement links being made more efficient/safe. 
         Information from areawide agencies can be useful.
____________________

12.   Trends in Real Estate.  1984, Real Estate Research Corporation,
      November 1983.

                                   C-2



                                TABLE C-1
                        EXAMPLE OF TECHNIQUE FOR
          ESTIMATING OFFICE BUILDING PEAK HOUR GENERATED TRIPS

      þ  GROSS FLOOR AREA (SQ. FT.)     62,000       [1]
      þ  SQ. FT. /EMPLOYEE                 275       [2]
      þ  TOTAL NUMBER OF EMPLOYEES         225       [3]

      þ MODE OF ARRIVAL        PERCENT SPLIT    NUMBER OF PERSONS
      Bus                         4.0                   9
      Subway and Light Rail       0.0                  --
      Walk/Other                  1.0                   2
      Vanpool                     3.0                   7

      Auto                       92.0                 207  
                               --------             ---------
                                100.0 [4]             225  [5]

      þ  AVERAGE DAY EMPLOYEES (with 10 percent absentees)
                                Vanpool                 6
                                 Auto                 186  [6]

                                VEHICLE
      þ  VEHICLE TRIP ESTIMATESOCCUPANCY RATE PERSONS     VEHICLES

         Vanpool                  7.0            6            1
         Auto                     1.25 [7]     185 [8]      143 [9]
                                               144 

      þ  AM PEAK HOUR        ARRIVAL RATE     VEHICLE       TRIPS
      Employee Vehicle Trips      55% [10]      79          [11]
      Non-employee vehicle trips  10%            6          [12]
      (0.28 trips/employee)                    ----
      Total inbound trips                       85          [13]
      Total outbound trips                      15          [14]
                                               ----
      AM Peak Hour 2-way trips                  100         [15]

      þ PM PEAK HOUR        DEPARTURE RATE    VEHICLE       TRIPS
      Employee Vehicle Trips      50% [16]      72          [18]
      Non-employee vehicle trips     20% [17]   12          [19]
      (0.28 trips/employee)                    ----
      Total outbound trips                      84          [20]
      Total inbound trips                       15          [21]
                                               ----
      PM Peak Hour 2-way trips                  99

      þ  VEHICLE TRIP RATE/1,000 SQ. FT. (2-WAY)
         AM Peak Hour         1.61  [22]
         PM Peak Hour         1.58  [23]

                       Step numbers in [Brackets]

                                   C-3



Step 5:   Apply the mode of arrival percentage to the total number of
          employees to achieve the total number of employees arriving
          by mode on a typical day; assuming full employment.

Step 6:   A 10 percent reduction factor is applied to the total number
          of employees arriving by vanpool and auto results to reflect
          the fact that on a typical weekday, 10 percent of the
          employees will be absent due to sickness, vacation,
          traveling on business etc.

Step 7:   Select reasonable auto and vanpool vehicle occupancy rates
          in persons/vehicle using data from areawide agencies.

Step 8:   Select the number of persons arriving by vanpool and auto
          from Step 6.

Step 9:   Divide Step 8 persons by the Step 7 occupancy rates to
          determine the number of vehicles (other than buses) arriving
          at the site.

Step 10:  The percentage of employee vehicle trips arriving during the
          AM peak hour is selected using historical, survey, or
          information from areawide agencies.  This is an important
          percentage which may range from 45 to 65 percent.  For
          example, an office building with 24 hour computer operations
          will create a significantly lower AM peak hour percentage
          than a normal office building.

Step 11:  Applying the Step 10 percentage to the Step 9 average day
          vehicle trips results in the AM peak hour employee vehicle
          trips.

Step 12:  To account for non-employee trips, such as visitors,
          maintenance or delivery trips per employee during the AM
          peak hour, a rate is selected based on historical, survey,
          areawide data or experienced judgment.  In the example 0.28
          trips per employee was selected along with 10 percent of the
          trips arriving during the AM peak hour.

          Applying the 0.28 trips per employee to the 225 total
          employees results in 63 daily trips; with 10% (or 6)
          arriving during the AM peak hour.

Step 13:  Adding the employee and non-employee vehicle trips results
          in the total inbound or arriving trips.

                                   C-4



Step 14:  On the basis of other surveys, ITE or updated NCHRP 187
          data, compute the % inbound/outbound peak hour trips.  In
          this example, approximately 15% of the total trips are
          outbound.  Since the total trips are not known at this
          point, a simple equation determines this volume.

                        X  = Total (in and out) Trips
                       85  = Inbound Trips (from Step 13)

                85 + .15x  = x
                       85  = X - .15X
                       85  = .85X
                      100  = X
                 100 - 85  = 15 outbound trips

Step 15:  Adding the 85 inbound and 15 outbound trips results in the
          total AM trips.

Step 16 thru 21:
          A process similar to Steps 10-15 is used except the
          "departure" rate is reduced based on ITE, updated NCHRP 187
          data or local surveys.  In the example this is assumed to be
          50% rather than the 55% AM arrival rate.

Step 22:  Calculate the AM peak hour trip generation rate by dividing
          the 100 inbound and outbound AM peak hour trips generated by
          62,000 square feet (Step 1) which results in 1.61 trips per
          1000 gross square feet.

Step 23:  Repeat the Step 22 calculations using 98 PM peak hour trips
          generated by 62,000 square feet (step 1) which results in
          1.58 trips per 1000 gross square feet.

This procedure for estimating office generated peak hour traffic is
essential when TSM, transit or subway ridership is a significant
factor.  It also is a basis for modifying such factors over a 15 to 20
year period to reflect important changes in employee modes of travel. 
The effect of various factors on the trip rate is evident using
sensitivity analyses.

TRIP DISTRIBUTION/ASSIGNMENT

Once the peak hour trips to be generated are estimated, it is
necessary to determine the geographic distribution.  For example, for
residential uses, where will the residents work?  For office uses,
where will the employees live?  This can be achieved by considering
one of the following techniques.

                                   C-5



1. Trip distributions based on previous studies, i.e. the percentage
   of generated site trips using each site approach corridor, as
   documented in previous studies for nearby sites.

2. Experienced judgment and knowledge of local conditions.

3. A combination of 1 and 2.

4. Using a special zip code analysis for a representative land use.

5. Item 4 plus a housing analysis if a 20-year study period will
   change the trip distribution pattern significantly.

6. Areawide travel model results including trip tables by trip
   purpose.

7. Gravity Model (Quick Response System or NCHRP 187)

The trip distribution percentage is applied to the generated inbound
(to) and outbound (from) development trips, and the results are
assigned to the road network.  The results for a geographic
distribution of trips for a 62,000 square foot office building on a
basic road network are shown on the top of Figure C-1 for the AM peak
hour.  The results of applying the percentages to the estimated total
two-way trips and assigning them to the road network are shown at the
bottom of Figure C-1.  Note that if a road link is one way, the
inbound and outbound assignments do not use the same links, so care
must be taken to balance the network.  Of course, turn restrictions
and other elements can complicate the assignment process.

To illustrate how trip distributions may vary over a 15 to 20 year
period in a complex site access study see Figure C_ 2. This shows the
office trip distribution as a percent of the total trips on the three
road networks previously described in Figures 4a, 4b, and 4c in
Chapter III.

Several items should be noted in reviewing Figure C-2.

   -  The example is for the 62,000 square foot office building to
      show how access routes change over-time.
   -  Only inbound percentages have been indicated.
   -  The geographic distributions vary between short term and long
      term to represent a shift in housing opportunities for office
      building employees.
   -  The road networks vary between short, mid and long terms.

                                   C-6



                               FIGURE C-1
          EXAMPLE OF GEOGRAPHIC DISTRIBUTION OF OFFICE BUILDING
                   GENERATED TRIPS DURING AM PEAK HOUR


Click HERE for graphic.


                                   C-7



                               FIGURE C-2
          EXAMPLE OF GEOGRAPHIC DISTRIBUTION OF SITE GENERATED
       TRAFFIC, AS A PERCENT OF TOTAL INBOUND TRIPS GENERATED, FOR
               SHORT, MID TERM AND LONG TERM ROAD NETWORKS


Click HERE for graphic.


                                   C-3



   -  The "building" entrance inbound volumes vary from 65/35 in short
      term; to 60/40 in mid-term; to 57/43 in the long term.
   -  This process must be repeated for not only site trips, but other
      new development trips in a complex study.
   -  Following the percent distributions, generated traffic for all
      sites must be assigned to the road network.

This series of analyses results in site related peak hour traffic road
network assignments which are now sufficiently compatible for merging
with Phase II results.

LEVELS OF SERVICE

The levels of service can be computed manually for basic site access
studies.  For complex studies, tabulations and level of service
calculations can be performed using the computer with technical
refinements tested manually against design options.  Also unique
solutions requiring considerable level of service experience will
undoubtedly have to be evaluated.  How the level of service
calculations are performed are subject to local guidelines because
there is some difference of opinion as to the merits of various
techniques.  Two techniques are usually acceptable:

   -  Highway Capacity Manual: Operation/Design
   -  Highway Capacity Manual: Planning Analysis

A combination of both methods is sometimes used.  While the
Operation/Design approach must be used if freeway ramps and weaving
sections are involved; the Planning Analysis can be used for at-grade
intersections.  The Transportation Research Board (TRB) is in the
process of releasing updated highway capacity manuals that conform to
the new standards.  Prior to this, the methods were found in the 1965
Highway Capacity Manual and TRB Circular 212.

The Operation/Design method uses six level of service categories, A
thru F:

   -  Level of Service A:  a condition of free flow with low traffic
      density, where no vehicle waits longer than one signal
      indication.
   -  Level of Service B:  stable flow of traffic where only on a rare
      occasion do drivers wait through more than one signal
      indication.

                                   C-9



   -  Level of Service C:   still in the zone of stable flow, but
      intermittently drivers must wait through more than one signal
      indication and backups may develop behind left turning vehicles.
   -  Level of Service D:  approaching instability; drivers restricted
      in their freedom to change lanes and delay approaching vehicles
      may be substantial during peak hour.
   -  Level of Service E:  traffic volumes are near or at capacity on
      the arterial and long queues of vehicles may create lengthy
      delays especially for left turning vehicles.
   -  Level of Service F:  congested condition of forced traffic flow,
      where queued backups from locations downstream restrict or
      prevent movement of vehicles out of the approach, creating a
      storage area during part or all of the peak hour.

These six categories are used in most site access studies.  Oftentimes
Level of Service D is adopted by public agencies as the maximum Level
of Service acceptable in an urban area and Level of Service C in a
rural area.  The six categories have provided an excellent basis for
negotiations.  The Planning Analysis method uses three descriptive
categories: Below Capacity (level of service At B. or C); Near
Capacity (LOS D/E); and Above Capacity (LOS E/F).

The local/state ordinances and requirements should be used in
calculating Level of Service.  It is possible, as with the two current
methods for calculating Level of Service, that some agencies will
continue to require the guidelines considered most appropriate to
their local or state situation.

                                  C-10



                               APPENDIX D
CASE STUDIES

Recognizing the need to show the application of trip generation rates
and to test the sensitivity of levels of service to a variation in
trip generation rates, trip distribution patterns and normal growth
rates, four case studies were conducted.  These case studies represent
three of the more prominent land uses,

   1. A mall site expansion in the suburbs of a small city
   2. A mixed use project on the outskirts of a small town
   3. A multi-tenant office park in a suburban area
   4. A mixed use project containing hotel, offices, residential and
      retail uses in a suburban area.

The first case study is illustrated using the seven step site access
study process.  The other three case studies, although addressing all
phases of the process, are formatted as follows:
   -  summary of technical issues
   -  level of service sensitivity tests
   -  level of service sensitivity results
   -  summary of findings


CASE STUDY NO. 1:  OFFICE COMPLEX/MOTEL

Site Access Study Process

To illustrate how the basic site access study process, described in
Chapter III, and summarized in Figure 2 applies, the various technical
elements of each phase are described below for Case Study No. 1.

Phase I. -  Establish Study Design and Verify Existing Peak Hour
            Traffic Situation

The site development program was first confirmed with the client to
establish the proposed new land uses/density and build out year.
   -  Two new office buildings (total 100,000 gross sq. ft.)
   -  A 109 room motel
   -  All three facilities would be completed within two years on out
      parcels surrounding a small regional mall already in existence.
   -  Appropriate mall site plans were also obtained to understand the
      roadway and lane configuration.  A site reconnaissance was also
      performed, and a meeting held with the site engineer and
      architect.

                                   D-1



Since the mall already existed, the site access needs associated with
the new office and motel uses were very closely related to the base
peak hour mall traffic.  Also, the study area was less complicated
because it was principally within the confines of the mall property
and the uses could be built as-zoned.  The issue with local (County
and State) officials was simply,  1)  would the new uses create
significant peak hour impact; and  2)  if the impact was significant
what roadway improvements, by the mall owner, on the mall roadway
network or at key intersections, would be necessary to achieve
acceptable peak hour traffic conditions after completion of the office
buildings and the motel?

The key issue with the client was to select a representative situation
to collect new peak hour mall and office traffic.  Fortunately, the
study began in the winter, so March was selected for an AM and PM peak
hour traffic count at key intersections.  November (Thanksgiving)
through December (Christmas) counts were to be avoided, if possible
since these mall volumes do not represent design day conditions but
are instead peak shopping (traffic) conditions.  Since the new office
would only generate traffic on weekdays, a Friday was selected for the
mall traffic counts in March.  While mall traffic would be higher on a
Saturday, the office uses would not be significantly occupied.  The
motel was considered to generate an insignificant amount of peak hour
traffic on a Saturday.  Conversations with local (County and State)
officials were minimal since the study area was so well defined; and
re-zoning was not an issue.  The review process for the technical
traffic information was discussed; including buildout year, land
uses/density, annual growth rates and other proposed development.

Five intersections were included for analysis (See Figure D-1).
   -  Intersection 1 - The main access to the mall site via a heavily
      traveled, four lane, undivided major arterial.
   -  Intersection 2 - The major point of convergence for mall traffic
      to and from the major arterial as well as the sole access route
      to the motel site.
   -  Intersections 3 & 4 - Secondary access points to the mall site
      from the lightly traveled four lane, undivided minor arterial.
   -  Intersection 5 - The sole access to the office park site at the
      end of a major collector street.

                                   D-2



                               FIGURE D-1
                            CASE STUDY NO. 1
                     SITE LOCATION AND ROAD NETWORK


Click HERE for graphic.


                                   D-3



Peak period 7:00-9:00AM and 4:00-6:00PM turning movement counts were
made at all key intersections on a Friday in March.  Tabulations
indicated peak hours to be 7:15-8:15AM and 4:30-5:30 PM. All locations
operated at level of service A during both peak hours.  TRB Circular
212 was used for the calculations.  No adjustments were made in the
March mall traffic since this month was considered to be
representative of an average or typical month for malls, according to
information from Urban Land Institute and Institute of Transportation
Engineers.  While no significant site access constraints were
identified in this process, operations at intersections 1 and 2 were
more carefully analyzed because the motel would create a new entrance
at intersection 2, and possibly influence the efficiency of
intersection 1.

Phase II. - Project Future Peak Hour Traffic Situation Without Site(s)
            Developed

This phase primarily involved the comparison of available data to
establish annual growth rates.  For example, the state highway
department had a 12 hour Tuesday turning movement count for inter-
section 1; exactly one year earlier (in March).  A direct month to
month weekday comparison was therefore possible to the new data
obtained in Phase I. The annual increase in traffic was therefore
substantiated.  It was decided that 1984 major arterial through
traffic would be increased +11% per year (or a total of +22%), to
achieve 1986 traffic, which would reflect new growth beyond the
subject site.

At the other four locations a +3% per year growth (or +6% total) was
used.  The 1984 volumes, except for mall volumes, were increased    to
1986 AM and PM peak hour volumes and the levels of service    
calculated. without the office and motel sites developed, all
intersections would operate at level of service A during the AM peak
hour.  Intersection would operate at level of service B during the PM
peak hour with all other intersections operating at level of service
A. The Highway Capacity Manual was used for the level of service
calculations.

Phase III. -   Project And Distribute Peak Hour Site Development
               Traffic

The following process was used to estimate the AM peak hour trips to
be generated by new office and motel facilities.

                                   D-4



                           AM         Total
                         Two Way     Two Way   %       No.     %     No.
                        Trip Rate     Trips   In       In     Out    Out

 Office: 100,000
 Sq. Ft.             2.50/1,000SqFt    250    85       213    15     37

 Motel: 109 Rooms       0.66/room      72     50       36     50     36

For the PM peak hour, the following process was used to estimate the
PM peak hour trips to be generated by new office and rental
facilities:

                           PM         Total
                         Two Way     Two Way   %       No.     %     No.
                        Trip Rate     Trips   In       In     Out    Out
 Office: 100,000
 Sq. Ft.             2.82/1,000SqFt    282    14       40     86     242

 Motel: 109 Rooms       0.59/Room      64     50       32     50     32

The motel was assumed to have no restaurant or meeting facilities. 
Trip rates were in conformance with ITE data and acceptable to local
officials.[14]  No reduction was taken for trips between the land uses
within the site (internal trips).

The geographic distribution was based on familiarity with the local
housing market and travel patterns and inputs from the County
officials.  The new trips were then assigned to the road network --
which was essentially unchanged from the 1984 network, although a
fourth leg was added at both Locations 2 and 5.


Phase IV. - Project Future Peak Hour Traffic Situation with Site(s)
            Developed

Phase II and III results for the AM and PM peak hours were next
combined to represent conditions with the office and motel sites
occupied in 1986.  The AM peak hour was again found to result in Level
of Service A at all intersections; however, during the PM peak hour,
Level of Service B occurred at both intersections 1 and 2.


Phase V. -  Develop Site Access Related Solution

It was concluded that acceptable levels of operating efficiency
____________________

14.   Trip Generation., An Informational Report, Institute of
      Transportation Engineers, Washington D.C., 1982

                                   D-5



would be achieved in 1986 with the new facilities constructed and
occupied.  Existing roadway geometrics were considered to be
sufficient for 1986 conditions.  A solution which involved new roadway
or traffic operational improvements considered necessary in
conjunction with the new development was not necessary -except for the
roadway and entranceway connections necessary to serve the office and
motel sites.

LOS Sensitivity Tests

Because of the relatively straight-forward nature of the development
proposal, this case study provides an excellent opportunity for
testing the sensitivity of level of service variations for three
fundamental components of a site access study:  1) trip generation
rates, 2) the trip distribution pattern and 3) normal (traffic) growth
rates.  Four conditions were evaluated as described below and
summarized on Table D-1:

   -  Condition 1: This is the "worst case" condition, involving high
      office and motel site trip generation rates; (Distribution A.
      Figure D-2) a geographic distribution with 75% of office site
      generated traffic passing through the most heavily traveled
      intersections (1 & 2); and high normal growth rates for both
      through traffic on adjacent arterials and (existing) mall site
      traffic.  Distribution A reflects the current distribution of
      mall site traffic.

   -  Condition 2: This condition is the same as Condition 1 except
      that office and motel generated traffic rates have been reduced
      to those shown in updated NCHRP 187. [15]

   -  Condition 3: This condition uses the updated NCHRP 187 Table 1
      trip  generation rates, as in Condition 2, but the distribution  
      of office site generated traffic, at intersections 1 & 2, has
      been reduced to 55% to reflect greater use of the minor
      arterial; see "B" Trip Distribution (Figure D-3).

   -  Condition 4: This condition is the same as Condition 1 except
      for reduced rates of normal growth for arterial through traffic
      and mall site traffic.  The 2.7% annual growth rate for arterial
      through traffic was based on a long range, regional forecast of-
      traffic on the major arterial performed by the state.  The mall
      site traffic growth rate was also reduced to approximately one-
      half of Conditions 1, 2 and 3.
____________________

15.   Development And Application Of Trip Generation Rates, Federal
      Highway Administration (HHP-22), January 1985

                                   D-6



                                TABLE D-1
                            CASE STUDY NO. 1
                    ALTERNATIVE CONDITIONS EVALUATED

CONDITION    Description
   1         ITE Rates
   þ         Updated NCHRP 187 Rates
   þ         Updated NCHRP 187 Rates + Modified Trip Distributions
   þ         Reduced Growth Rates

                                CONDITION
                    1               2              3               4

TWO WAY
SITE TRIP
GENERATION RATES

OFFICE (trips per 1000 gross sqft.)
   AM peak hour   2.50            1.98           1.98            2.50
   PM peak hour   2.82            1.93           1.93            2.82

MOTEL (trips per room)
   AM peak hour    .66             .52            .52             .66
   PM peak hour    .59             .54            .54             .59

SITE TRIP
DISTRIBUTION
PATTERN            "A"             "A"            "B"             "A"
             See Figure        See Figure     See Figure      See Figure
                   D-2             D-2            D-3             D-2

ARTERIAL TRAFFIC
NORMAL ANNUAL GROWTH
RATE
   AM peak hour   +11%            +11%           +11%            +2.7%
   PM peak hour   +18%            +18%           +18%            +2.7%


MALL SITE
NORMAL ANNUAL GROWTH
RATE
   AM peak hour    +3%             +3%            +3%             +2%
   PM peak hour   +10%            +10%           +10%             +5%

                                   D-7



                               FIGURE D-2
                            CASE STUDY NO. 1
                        "A" TRIP DISTRIBUTION FOR
                    OFFICE AND MOTEL GENERATED TRIPS
                         (EXISTING SITUATION AND
                          CONDITIONS 1, 2, & 4)


Click HERE for graphic.


                                   D-8



                               FIGURE D-3
                            CASE STUDY NO. 1
                        "B" TRIP DISTRIBUTION FOR
                    OFFICE AND MOTEL GENERATED TRIPS
                              (CONDITION 3)


Click HERE for graphic.


                                   D-9



LOS Sensitivity Results

Table D-2 shows the resulting levels Of service and critical lane
volumes for Conditions 1 through 4 at all five intersections.  The
only intersections that operate at a level of an D are Intersections 1
and 2, and this occurs only during the PM peak hour.  During the AM
peak hour all Intersections operated at Level of Service A, regardless
of the condition tested.  During  the PM peak hour at Intersection 1,
the Condition 1 LOS F, is improved to an E, with the office and motel
site traffic generation rates reduced by approximately 20% (Condition
2).

The Level of Service remains E, however, even though the office site
traffic is re-assigned to the intersection after changing the
distribution pattern from 75% to 55% (Condition 3). If the anticipated
growth in arterial through traffic and mall site traffic is not
achieved (Condition 4), a very much improved Level of Service C/D is
produced, even with high site traffic generation rates and a high
percentage of site traffic assigned to the intersection.

For Intersection 2:  Condition 1, LOS E remains even after the office
and motel site generated traffic is reduced by 25% (Condition 2). 
Reduction of the trip generation rate and trip distribution improves
the Condition 1 Level of Service E to a Dr (Condition 3). 
Approximately the same effect is achieved if the anticipated rate of
growth in through and mall site traffic is not achieved (Condition 4).

Summary

A difference of 20% in the trip generation rate, combined with a 20%
variation in the trip distribution pattern changes forecast
intersection traffic sufficiently to effectuate a change of one level
of service.  However, variations in the normal growth rate revealed an
even greater change in level of service results.

                                  D-10



                                TABLE D-2
                            CASE STUDY NO. 1
     PEAK HOUR LEVEL OF SERVICE COMPARISON FOR CONDITIONS 1, 2, 3, 4

     LEVEL OF SERVICE AND CRITICAL LANE VOLUMES AT INTERSECTIONS 1-5

                              Intersection
 Cond-       1           2          3           4           5
 ition      AM   PM     AM  PM     AM  PM      AM  PM      AM  PM

   1         A           A          A           A           A
            509         508        244         245         540
                  F          E          A           A           A
                1447       1414        539         502         601

             A           A          A           A           A
   2       1476        1467       1240        1239        1485
                  E          E          A           A           A
                1377       1293        538         485         483

   3         A           A          A           A           A
           1446        1371       1245        1291        1485
                  E          D          A           A           A
                1322       1203        543         543         359

             A           A          A           A           A
   4       1440        1540       1185        1209        1540
                 C/D         D          A           A           A
                1138       1259        374         364         563

                                                (PHASING)
             3 PHASE     3 PHASE    2 PHASE     2 PHASE     2 PHASE

                        LEVEL OF SERVICE CRITERIA
                             (Vehicles/Hour)

                             3 PHASE                   2 PHASE
              LOS
               A            0  - 855                  0  - 900
               B          855  -1000                900  -1050
               C         1000  -1140               1050  -1200
               D         1140  -1275               1200  -1350
               E         1275  -1425               1350  -1500
               F         1425 -ABOVE               1500 -ABOVE

                                  D-11



CASE STUDY NO. 2: MIXED USE PROJECT NEAR SMALL TOWN

Summary of Technical Issues

A mixed use project involving 757 apartments/condominiums, 214 single
family attached dwelling units and 9.3 acres of light
industrial/office space was proposed to be developed adjacent to a
major arterial road near an Interstate highway (See Figure D-4).  Key
issues involving the project are described below:

   -  The residential development would have access to the major
      arterial solely via the minor collector shown on Figure D-4. 
      The light industrial/office space would have access via the
      major collector and the minor collector.  This access routing
      detail was a function of the site plan road network.
   -  At the time of the development proposal, roadway widening
      improvements at Intersection 1 were committed by the state and
      other developers.  Improvements at Intersection 2 were also
      being proposed in conjunction with this development since a
      fourth leg was being added to the intersection.
   -  The geographic distribution of site traffic is shown on Figure
      D-5.  Industrial (office) traffic was assigned to the major
      collector and residential traffic was assigned to the minor
      collector.  The same distribution patterns were used based on
      technical judgment regarding employment and housing
      opportunities.
   -  Corridor growth in the area was creating a worsening traffic
      situation on the major arterial, particularly for the four year
      traffic forecast anticipated at full development of the site.

LOS Sensitivity Tests

In order to determine the effect of variations in trip generation
rates on the two intersections, five alternative trip rate conditions
were evaluated.  Normal growth rates, road improvements, site traffic,
and trip distribution patterns are the same for all five conditions.

These five conditions are described below and summarized in Table D-3:

   -  Condition 1: The trip generation rates for both residential and
      industrial/office uses are the same as those used in the
      original site evaluation, and as accepted by the local
      jurisdiction.  The original site evaluation used "per acre" trip
      rates for the light industrial development and also stated a
      floor area ratio

                                  D-12



                               FIGURE D-4
                            CASE STUDY NO. 2
                       SITE LOCATION WITH RESPECT
                             TO ROAD NETWORK


Click HERE for graphic.


                                  D-13



                               FIGURE D-5
                            CASE STUDY NO. 2
                 GEOGRAPHIC DISTRIBUTION OF SITE TRAFFIC


Click HERE for graphic.


                                  D-14



                               TABLE D-3a
                            CASE STUDY NO. 2
            AM/PM PEAK HOUR TRIP GENERATION RATES BY LAND USE
                       FOR ALTERNATIVE CONDITIONS

                                          LAND USE
                         Apartment /       Single          Light
                         Condominium       Family       Industrial
                                          Attached         Gross
                                                         (per 1000
   CONDITION             (per unit)      (per unit)      sq. feet)

       1
 AM Trip Rate               0.44            0.56           0.65
 PM Trip Rate               0.55            0.67           0.58

       2
 AM Trip Rate               0.48            0.62           0.65
 PM Trip Rate               0.61            0.74           0.58

       3
 AM Trip Rate               0.40            0.50           0.65
 PM Trip Rate               0.50            0.60           0.58

       4
 AM Trip Rate               0.44            0.56           0.95
 PM Trip Rate               0.55            0.67           0.88

       5
 AM Trip Rate               0.55            0.44           0.95
 PM Trip Rate               0.71            0.54           0.88

                                  D-15



                               TABLE D-3b
                            CASE STUDY NO. 2
                  AM/PM PEAK HOUR COMPARISON OF TRAFFIC
                  GENERATED FOR ALTERNATIVE CONDITIONS

                                   GENERATED SITE TRAFFIC
                       TOTAL     PEAK HOUR        PEAK HOUR   % CHANGE
                      TRAFFIC    RETAINED         EXTERNAL    OFF SITE
                                  ON SITE        (OFF SITE)     FROM
                                                              CONDITION
    CONDITION                                                     1

        1
    AM Trips            559          0               559        n.a.
    PM Trips            653          0               653        n.a.

        2
    AM Trips            605          0               605        8.0%
    PM Trips            709          0               709        9.0%

        3                
    AM Trips            513         01               513        -8.0%
    PM Trips            597          0               597        -9.0%

        4
    AM Trips            607          0               607        9.0%
    PM Trips            702          0               702        8.0%

        5
    AM Trips            664         78               508        -9.0%
    PM Trips            787         72               653        0.0%

                                  D-16



      of 0.4. The "Per acre" rates have been converted to "per 1,000
      gross square foot" rates based on the stated floor area ratio.

   -  Condition 2: The residential trip generation rates were
      increased 10% over Condition 1 rates.  The light industrial trip
      generation rates are the same as those used in Condition 1.

   -  Condition 3: The residential trip generation rates were
      decreased 10% below Condition I rates.  The light industrial
      trip generation rates are the same as those used in Condition 1.

   -  Condition 4: The residential trip generation rates are the same
      as those used in Condition 1. The light industrial trip
      generation rates were obtained from updated NCHRP 187.  The
      light industrial office trip rates are approximately 50% higher
      than those used in Conditions 1, 2 and 3.

   -  Condition 5: Both residential and light industrial  trip
      generation rates were obtained from updated NCHRP   187.  Also
      note that external site traffic was reduced to account for work
      trips between the residential and light industrial components of
      this proposed development.  The basis for determining traffic
      retained on-site is shown in Table D-4, and is based on factors
      presented in Table 6 of Development and Application of Trip
      Generation Rates," prepared for Federal Highway Administration
      in January 1985.  The reduction from total traffic generated to
      net external traffic was based on the internal traffic estimate
      for industrial use, because the internal traffic estimate for
      residential use is nearly equal to or exceeds the total traffic
      generated for the industrial use in all cases.

LOS Sensitivity Results

Table D-5 shows the resulting levels of service and critical lane
volumes for Conditions I through 5 at Intersections 1 and 2. During
the AM peak hour both Intersections I and 2 operate at acceptable
Levels of Service (B or B/C and A, respectively) under all five
conditions.  The only variation based on different conditions occurs
at Intersection 1, where the higher traffic generated under Conditions
2 and 4 results in a slightly reduced level of service.

During the PM peak hour, Intersection 2 would operate at a minimally
acceptable Level of Service D under all conditions despite a
substantial variation in PM peak hour external site traffic (see Table
D-4).  Intersection I operates at a Level of Service E under all
Conditions except Condition 3. which

                                  D-17



                                TABLE D-4
                            CASE STUDY NO. 2
                 CONDITION 5: INTERNAL/EXTERNAL TRAFFIC

                   PEAK HOUR VEHICULAR TRIPS GENERATED

                           AM                              PM
                   IN              OUT            IN              OUT
757  APARTMENT     68              348            371             167
     UNITS

214  SINGLE FAMILY
     ATTACHED      15              79             77              39
     UNITS

TOTAL
     RESIDENTIAL   83              427            448             206
     UNITS

162,000 GROSS
     SF LIGHT      133             21             31              112
     INDUSTRIAL


                 INTERNAL (ON-SITE) TRAFFIC ESTIMATE [1]

  RESIDENTIAL     (55%)           (25%)          (40%)           (50%)
                   46              107            179             103

  INDUSTRIAL      (50%)           (80%)          (80%)           (50%)
                   67              11             16              56

           INTERNAL (ON-SITE TRAFFIC ADJUSTED ME DENSITIES [21

  RESIDENTIAL      11              67             56              16
  INDUSTRIAL       67              11             16              56

                     NET EXTERNAL (OFF-SITE) TRAFFIC

  RESIDENTIAL      72              360            392             190
  INDUSTRIAL       66              10             15              56

  [1]  Table 6, Development and Application of Trip Generation Rates,
FHWA, January 1985
  [2] Since there are only two land uses, the inbound internal trips
to the residential area are outbound internal trips from the
industrial area, and vice-versa.

                                  D-18



                                TABLE D-5
                            CASE STUDY NO. 2
               PEAK HOUR LEVEL OF SERVICE FOR CONDITION 1
           Level of Service and Critical Lane Volume Summation
                              Intersection
                            1                               2
  Condition        AM                PM           AM              PM
  ----------    ------------ ------------       ------------ -----------
                    B                              A
     1             986                            741
                                    E                              D
                                  1287                           1218

                   B/C                             A
     2             991                            727
                                    E                              D
                                  1298                           1222

                    B                              A
     3             981                            757
                                   D/E                             D
                                  1277                           1214

                   B/C                             A
  4               1010                            750
                                    E                              D
                                  1287                           1230

                    B                              A
     5             971                            730
                                    E                              D
                                  1289                           1217

                                    (PHASING)
                    3 PHASE                              3 PHASE

                        LEVEL OF SERVICE CRITERIA
                             (Vehicles/Hour)
                                 3 PHASE
                   LOS
                    A       0       -             855
                    B      855      -            1000
                    C     1000      -            1140
                    D     1140      -            1275
                    E     1275      -            1425
                    F     1425      -            ABOVE

                                  D-19



involves the lowest level of external site traffic.  Under Condition
3, Intersection 1 operates at a D/E Level of Service.

Summary

This case study indicated that a variation in external trip generation
rates by plus or minus eight or nine percent did not have a very
significant effect on the resulting peak hour levels of service.  In
instances where the critical lane volume is within fifteen or twenty
vehicles of a level of service limit, there is an indication that an
eight or nine percent variation in trip rates will cause a level of
service change of only one-half level.

CASE STUDY NO. 3: OFFICE MULTI-TENANT

Summary of Technical Issues

Two major corporations combined development efforts to re-zone two
corner tracts of land (tracts A and B) at a major at-grade
intersection west of a major Interstate (freeway) interchange. 
Several issues made the situation extremely complex as illustrated in
Figure D-6 and described below:

   -  To the east of the Interstate interchange, a very major rezoning
      had been recently approved to permit a major office park and
      hotel complex to be constructed.  As a condition of this re-
      zoning, the developers agreed to construct a new interchange as
      an extension of the Interstate interchange.  A major ridesharing
      program was also proffered to reduce PM peak hour traffic and to
      allow the "extended" interchange to operate at LOS D in PM peak
      hours.  This proffer was unusual since this tract was termed
      almost inaccessible prior to re-zoning.
   -  The state highway department was committed to construct a second
      interchange to replace the (existing) major at-grade
      intersection west of the Interstate interchange* This re-
      construction would occur next to the tracts subject to rezoning
      with construction impacting the site plans.  The interchange
      would be identical in concept to the "extended" interchange
      except public funds would be used rather than private funds.
   -  Both interchanges are currently under construction.
   -  Besides the two subject sites A & By there were two adjacent
      tracts C and D which could potentially be re-zoned as office
      parks, so it was agreed with the local reviewing agency that all
      four tracts would be included in the site access analysis.  Re-
      zoning, however, only applied to tracts A and B.

                                  D-20



                               FIGURE D-6
                      LOCATION OF CASE STUDY NO. 3
                 SITE WITH RESPECT TO AREA ROAD NETWORK


Click HERE for graphic.


                                  D-21



   -  Re-development of tracts A and B was further complicated due to
      the fact that each tract involved an on-site road.  The fact
      that both roads were to be completed as part of each tract's
      development and then turned over to public agencies for
      maintenance, significantly influenced circulation patterns - as
      well as the trip distribution patterns for trips generated by
      all six tracts; A, B, C, D, E and F.
   -  Five other tracts were considered in the analysis for potential
      development: E. E G, H and I.
   -  Site C is currently a public school but may be available for re-
      development, as presumed in this study.

A summary of the tracts by land use type and Floor Area Ratio (FAR) is
indicated in Figure D-7; as agreed to with local review officials.

Additional technical information is summarized below:

   -  1987 was considered to be the build out year for all new
      developments.
   -  AM/PM peak hour trip generation rates of 1.39/1.27 (as developed
      used the Table C-1 office trip generation rate technique) were
      used for tracts A. B, C and D. The process for establishing
      these rates is shown in Table D-6.  Note  the corporate office
      space criteria of 325 square feet per employee.
   -  Slightly higher trip rates were used for other new developments. 
      The mode split of 13% bus and Metro/feeder bus was determined
      based on past experience with nearby development and agreement
      with local officials.  By 1987, Metro rail service will be
      available to the subject tracts via a Metro rail station
      approximately 1 mile to the north along the minor arterial
      highway (see Figure D-6).
   -  The general geographic distribution is-illustrated in Figure D-
      8.  It should be noted that site generated traffic for each
      tract was assigned separately, and with the truck related
      connector roads there were significant modifications.  The trip
      distribution patterns were based on basic patterns used in
      previous nearby studies and agreed to by local officials.
   -  The improved 1987 road network is illustrated in Figure D-9,
      along with intersection numbers for LOS reference.  Note that
      the new state highway department interchange will be completed
      by 1987, significantly improving an existing LOS F. Also note
      the on-site public roads would be completed connecting tracts A
      and C. and B and D. The five signals along the minor arterial
      would all operate as in an interconnected system.

                                  D-22



                               FIGURE D-7
                            CASE STUDY NO. 3
                   NEW DEVELOPMENT ANTICIPATED BY 1987


Click HERE for graphic.


 DEVELOPMENT TRACT   LAND USE    AREA RATIO  DENSITY

         A            Office        0.75     366,359  Gross Square Feet

         B            Office        0.75     691,623  Gross Square Feet

         C            Office        0.75     720,000  Gross Square Feet

         D            Office        0.70     337,500  Gross Square Feet

         E            Office        1.00     125,000  Gross Square Feet

         F           Townhouse       N/A     4-5,000  Gross Square Feet
                      office

         G          Industrial  (27.77 acre) 375,000  Gross Square Feet

         H            Office         N/A  Additional
                                              45,000  Gross Square Feet

         I            Office         N/A    As Zoned

                                  D-23



                                TABLE D-6
                            CASE STUDY NO. 3
                 SITE GENERATED AM/PM PEAK HOUR VOLUMES

                     OPTION ->    "A"        "B"        "C"       "D"
 * GROSS FLOOR AREA (SQ. FT.)   377359     691623     337500    720000
 * SQ. FT. / EMPLOYEE             325        325        325       325
 * TOTAL EMPLOYEES               1161       2128       1038      2215

 * MODE OF ARRIVAL    PERCENT   PERSONS    PERSONS    PERSONS   PERSONS

 Bus                   8.0%       93         170        83        177
 Metrorail/Feeder Bus  5.0%       58         106        52        111
 Walk/Other            0.5%        6         11          5        11
 Vanpool               3.0%       35         64         31        66
 Auto                  83.5%      970       1777        867      1850
 total                100.0%     1161       2128       1038      2215

AVERAGE DAY EMPLOYEES (10% absentees)
 Vanpool                          31         57         28        60
 Auto                             873       1599        780      1665
                       total      904       1657        808      1725

VEHICLE TRIP ESTIMATES occupancyVehicles  Vehicles   Vehicles  Vehicles
 Vanpool               10.00       3          6          3         6
 Auto                  1.30       671       1230        600      1281
 total                            674       1236        603      1287

 * OVERALL OCCUPANCY RATE        1.34       1.34       1.34      1.34

 * AM PEAK HOUR         Arrival Rate  =  66.00%

                               Vehicles   Vehicles   Vehicles  Vehicles
 Total Inbound Trips              445        816        398       849
 Total Outbound Trips             79         144        70        150
 AM Peak Hour 2-way Trips         524        960        468       999

 * PM PEAK HOUR         Departure Rate = 60.00%

                               Vehicles   Vehicles   Vehicles  Vehicles
 Total Outbound Trips             405        742        362       772
 Total. Inbound Trips             71         131        64        136
 PM Peak Hour 2-way Trips         476        872        426       908

 * TRIP RATE / 1000 SQ. FT. (2-WAY)
 AM Peak Hour                    1.39       1.39       1.39      1.39
 PM Peak Hour                    1.26       1.26       1.26      1.26

                                  D-24



                               FIGURE D-8
                            CASE STUDY NO. 3
                           GENERAL GEOGRAPHIC
                              DISTRIBUTION


Click HERE for graphic.


                                  D-25



                               FIGURE D-9
                            CASE STUDY NO. 3
                            1987 ROAD NETWORK


Click HERE for graphic.


                                  D-26



Level of Service Sensitivity Results

In order to determine the effect a change in the 1.39/1.27 (AM/PM peak
hour) trip rates would have on the level of service at the five key
intersections, the trip rates for tracts A, B, C and D were changed to
2.32/2.20, and 1.98/1.93 based on ITE and updated NCHRP rates,
respectively.  All other factors in the original analysis were left
unchanged.  This included the proposed road network.  The technique
for calculating level of service at the five interconnected signals
was particularly complex because originally the proposed highway
department phasing (without re-zoning and other new developments) had
to be modified to account for the re-zoned density and the other new
development.  The modified phasing and level of service with the
increased peak hour trips was based on the road network shown in
Figure D-9.  The results are shown in Table D-7 for four conditions.

Summary

 The level of service results indicate that the trip rates used in
 the negotiations (1.39/1.27), along with all the other technical
 factors, roadway geometrics and operational features achieved LOS D
 or better at all five locations.  The LOS D or better is a re-zoning
 criteria in the County where this study was performed.  This allowed
 a density of more than 2,000,000 gross square feet of new
 development to be built at the four tracts:

                                                          TOTAL SQ. FT.
    Tract A:      377,359          Tract C:      720,000
    Tract B:      691,623          Tract D:      337,500       2,126,482
                1,068,982  Sq. Ft.             1,057,000  Sq. Ft.

With the 1.39/1.27 rates replaced by the ITE rates of 2.32/2.20, two
key intersections become significantly more congested with LOS E,s at
locations 1 and 5. The intersection 1 level of service calculations
are very sensitive to any increase in "through" volumes along the
minor arterial corridor so when the trip rate was changed to the ITE
rater the Condition 1 LOS C/C (AM/PM) deteriorated to a LOS E/D. 
Increased trips generated by tracts D and B, becoming through trips at
intersection 1, were a reason for this increased congestion.  The
intersection 5 situation was impacted by increased traffic from all
four tracts.  These levels of service would have made the requested
densities unacceptable and may have led to either density reductions,
a change in land use mix or possibly a policy to have the developer
agree to TSM actions to reduce peak hour

                                  D-27



                                TABLE D-7
                            CASE STUDY NO. 3
      PEAK HOUR LEVEL OF SERVICE COMPARISON FOR CONDITIONS 1 THRU 4

                              Intersection
Cond-        1           2          3           4           5
ition       AM   PM     AM  PM     AM  PM      AM  PM      AM  PM

             C           B          C           A           C
   1       1032        1915       1046        1829        1028
                  C          A          B           A           D
                1012        797       1072         826        1155

             E          C/D         C           C           E
   2       1289        1142       1106        1103        1294
                  D          B          E           C           E
                1186        994       1317        1106        1313

             D           C          C           C           E
   3       1221        1049       1074        1046        1271
                  C          B          D          B/C          E
                1118        914       1230         993        1246

             D           C          C           B           D
   4       1197        1101       1031         921        1195
                  C          B          D           B          D/E
                1123        957       1249         874        1222

                                (PHASING)
          3  PHASE     3 PHASE     3 PHASE      3 PHASE      4 PHASE


                         CONDITION DESCRIPTIONS
                       Trip  Rates
      Condition         AM    PM    Comment
              1        1.39  1.27   Office Trip Rate Technique
                                    (Table D-6)
              2        2.32  2.20   ITE rates
              3        1.98  1.93   NCHRP 187 (updated)
              4        2.32  2.20   ITE / Reverse Analysis LOS D
                                    Density Reduced

                        LEVEL OF SERVICE CRITERIA
                             (Vehicles/Hour)

                                       3 PHASE         4 PHASE
            LOS          A           0 -   855       0 -   825
            LOS          B         855 -  1000     825 -   965
            LOS          C        1000 -  1140     965 -  1100
            LOS          D        1140 -  1275    1100 -  1225
            LOS          E        1275 -  1425    1225 -  1375
            LOS          F        1425 - ABOVE    1375 - ABOVE

                                  D-28



trips and hence improve the level of service to a LOS D. Note that
tract C was a County school, subject to possible rezoning at a future
date.  Using the updated NCHRP 187 trip rates (1.98/1.93) revealed the
fact that intersection 1 achieved acceptable LOS D/C, but intersection
5 is almost as congested as with the ITE rates WE).  To determine the
impact of the decision to use the ITE trip rates versus the local
1.39/1.27 trip rates, the level of service was set at the maximum LOS
D and solved for the maximum on-site density considering that both
intersections 1 and 5 must operate at maximum LOS D. These levels of
service results, indicated at the bottom of Table D-7, are obviously
LOS D or better.  However, to achieve this improved level of operating
efficiency, a reduction in density of approximately 18% was required.

                   Density
             Reduction Necessary
              To Achieve LOS D          Remaining
          At Locations 1 and 5          Density
Tract A                 0              377,359   Sq. Ft.
      B           190,000  Sq. Ft.     501,623   Sq. Ft.
      C            75,000  Sq. Ft.     645,000   Sq. Ft.
      D           115,000  Sq. Ft.     222,500   Sq. Ft.

                           TOTAL     1,746,482   Sq. Ft.

For tract B the 190,000 square feet represents a reduction of nearly
28% from the original density of 691,623, whereas tract A required no
reduction.  Of course to achieve LOS D. various mixed use options may
have resulted in acceptable peak hour trips; however, mixed use may
not have been marketable at this location or be a desired land use by
local officials.  Another alternative to retain this density, would be
to have the developer agree to institute TSM actions.

Finally, it should be noted that in actual fact after the rezoning for
tracts A and B was approved tract D was re-zoned as an office park. 
However, to receive approval the developer agreed to monitor trips
generated at certain stages of the development and if the trip rate
exceeded the 1.39/1.27 rates, TSM measures would be instituted.  There
was no cut off in density or any other rigid control after a specific
number of peak hour trips was reached.  This case study-indicates that
trip rate variation alone can have very significant financial/land
use/level of service implications in the site access study process.

                                  D-29



CASE STUDY NO. 4: MIXED USE PROJECT IN URBAN AREA

Summary of Technical Issues

The subject site is located along a major arterial highway, as
illustrated in Figure D-10, near an Interstate interchange and in an
urban setting.  Pertinent site characteristics were:

   -  The tract was zoned for officer hotel, commercial and
      residential use.  It was proposed, however, that the hotel be
      eliminated, retail space reduced, and office space increased.

   -  Local officials requested a complete site access study to verify
      changes in peak hour traffic conditions or roadway improvements
      associated with the proposed changes.

   -  Proposed site development for the build-out year 1990 included
      the following:

   + Residential
         High Rise Apartments  -  882 units
         Townhouses            -    8 units
      Total                                   890 units
   + Office                             1,027,617 square feet
   + Restaurant                               800 seats
   + Sporting (Athletic) Club              46,088 square feet

   -  The major arterial highway is currently a four lane divided
      facility but it will be widened to a six lane divided facility
      by 1990- with three interconnected traffic signals.  Public
      funds will be used for these improvements.

   -  The minor arterial roadway is currently a four lane divided
      roadway and would remain unchanged.

   -  A major collector road would be constructed as a four lane
      divided road by the developer of the subject tract and the
      developer of the tract immediately to the south.  The
      collector - minor arterial intersection would be signalized.

   -  Other new office development (by 1990) traffic, for the tract
      south of the subject tract was also considered in the traffic
      analyses because of the shared use of the new collector road and
      intersections.

   -  The subject site, when completed should be accessed via five
      entranceways and a major parking garage.

                                  D-30



                               FIGURE D-10
                            CASE STUDY NO. 4
                     SITE LOCATION AND ROAD NETWORK


Click HERE for graphic.


                                  D-31



   -  Local and regional bus service, including access to a Metro rail
      station, is available via the major arterial highway.

   -  The technical procedure used was similar to the complex site
      access study guidelines described earlier in this report; with
      the office trip generation rate technique used for estimating
      peak hour office generated traffic.  ITE trip rates were used
      for the other land uses.

LOS Sensitivity Tests

Since the variables tested in this case study relate only to the
office trip generation technique, it is necessary to explain how a
change in each variable resulted in a slightly different AM/PM peak
hour trip rate.  This is best illustrated by considering Tables D-8
through D-14; which represent Conditions A through C.

The 2-way trip rates per 1000 sq. ft. of gross office space are shown
below:

                         AM Peak Hour   PM Peak Hour
  CONDITION    A             1.56           1.46
  CONDITION    B             1.71           1.59
  CONDITION    C             1.38           1.29
  CONDITION    D             1.76           1.64
  CONDITION    E             1.83           1.73
  CONDITION    F             1.65           1.55
  CONDITION    G             1.22           1.11

Close review of tables D-8 through D-14 indicates the various factors
changed in developing the trip rate calculations.  The variables
considered were:

   -  Mode of Arrival/Departure Percentages

   -  Vehicle Occupancy Rates

   -  Peak Hour Arrival/Departure Rates

   -  Gross Square Feet Per Employee

                                  D-32



                                TABLE D-8
                            CASE STUDY NO. 4
                           BASE CONDITION - A

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  *  SQ. FT. / EMPLOYEE                                   265
  *  TOTAL EMPLOYEES                                     3878

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     6.5%         252
     Metrorail/Feeder Bus                    1.0%          39
     Walk/Other                              2.0%          78
     Vanpool                                 9.5%         368
     Auto                                   81.0%        3141
                             total         100.0%        3878

  * AVERAGE DAY EMPLOYEES ( 10% absentees)
     Vanpool                                              332
     Auto                                                2827
                             total                       3158

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                11.00         332         30
     Auto                                    1.25        2827       2262
                             total                                  2292

  OVERALL OCCUPANCY RATE                     1.38

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              55.00%                   1260
     Non-Employee                          10.00%                    106
     (@ .28 trips/employee)
               Total Inbound Trips                                  1366
              Total Outbound Trips                                   241
     AM Peak Hour 2-way Trips                                       1608

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                   1146
     Non-Employee                          12.00%                    130
            (@ .28 trips/employee)
              Total Outbound Trips                                  1276
               Total Inbound Trips                                   225
          PM Peak Hour 2-way Trips                                  1501

  * TRIP RATE / 1000 SQ. FT. (2-WAY)
                      AM Peak Hour                       1.56
                      PM Peak Hour                       1.46

                                  D-33



                                TABLE D-9
                            CASE STUDY NO. 4
                              CONDITION B:
                   CHANGE MODE-OF-ARRIVAL PERCENTAGES

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  * SQ. FT. / EMPLOYEE                                    265
  * TOTAL EMPLOYEES                                      3878

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     4.0%         155
     Metrorail/Feeder Bus                    2.0%          78
     Walk/Other                              1.0%          39
     Vanpool                                 3.0%         116
     Auto                                   90.0%        3490
                             total         100.0%        3878

  AVERAGE DAY EMPLOYEES ( 10% absentees)
     Vanpool                                              105
     Auto                                                3141
                             total                       3246

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                11.00         105         10
     Auto                                    1.25        3141       2513
                             total                                  2522

  * OVERALL OCCUPANCY RATE                   1.29

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              55.00%                   1387
     Non-Employee                          10.00%                    106
            (@ .28 trips/employee)
               Total Inbound Trips                                  1493
              Total Outbound Trips                                   264
          AM Peak Hour 2-way Trips                                  1757

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                   1261
     Non-Employee                          12.00%                    130
            (@ .28 trips/employee,
              Total Outbound Trips                                  1391
               Total Inbound Trips                                   246
          PM Peak Hour 2-way Trips                                  1637

  TRIP RATE / 1000 SQ. FT. (2-WAY)
     AM Peak Hour                                        1.71
     PM Peak Hour                                        1.59

                                  D-34



                               TABLE D-10
                            CASE STUDY NO. 4
                              CONDITION C:
              CHANGE MODE-OF-ARRIVAL AND VANPOOL OCCUPANCY

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  * SQ. FT. / EMPLOYEE                                    265
  * TOTAL EMPLOYEES                                      3878

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     9.0%         349
     Metrorail/Feeder Bus                    5.0%         194
     Walk/Other                              4.0%         155
     Vanpool                                12.0%         465
     Auto                                   70.0%        2714
                             total         100.0%        3878

  * AVERAGE DAY EMPLOYEES (10% absentees)
     Vanpool                                              419
     Auto                                                2443
                             total                       2862

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                10.00         419         42
     Auto                                    1.25        2443       1954
                             total                                  1996

  * OVERALL OCCUPANCY RATE                   1.43

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              55.00%                   1098
     Non-Employee                          10.00%                    106
      (@ .28 trips/employee)
              Total  Inbound Trips                                  1204
              Total Outbound Trips                                   212
      AM Peak Hour 2-way Trips                                      1416

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                    998
     Non-Employee                          12.00%                    130
            (@ .28 trips/employee)
              Total Outbound Trips                                  1128
               Total Inbound Trips                                   199
          PM Peak Hour 2-way Trips                                  1328

  * TRIP RATE / 1000 SQ. FT. (2-WAY)
                      AM Peak Hour                       1.38
                      PM Peak Hour                       1.29

                                  D-35



                               TABLE D-11
                            CASE STUDY NO. 4
                              CONDITION D:
                    CHANGE VANPOOL AND AUTO OCCUPANCY

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  * SQ. FT. / EMPLOYEE                                    265
  * TOTAL EMPLOYEES                                      3878

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     6.5%         252
     Metrorail/Feeder Bus                    1.0%          39
     Walk/Other                              2.0%          78
     Vanpool                                 9.5%         368
     Auto                                   81.0%        3141
                             total         100.0%        3878

  AVERAGE DAY EMPLOYEES ( 10% absentees)
     Vanpool                                              332
     Auto                                                2827
                             total                       3158

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                10.00         332         33
     Auto                                    1.10        2827       2570
                             total                                  2603

  * OVERALL OCCUPANCY RATE                   1.21

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              55.00%                   1432
     Non-Employee                          10.00%                    106
            (@ .28 trips/employee)
               Total Inbound Trips                                  1538
              Total Outbound Trips                                   271
          AM Peak Hour 2-way Trips                                  1809

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                   1302
     Non-Employee                          12.00%                    130
            (@ .28 trips/employee)
              Total Outbound Trips                                  1432
               Total Inbound Trips                                   253
          PM Peak Hour 2-way Trips                                  1685

  * TRIP RATE / 1000 SQ.  FT. (2-WAY)
                      AM Peak Hour                       1.76
                      PM Peak Hour                       1.64

                                  D-36



                               TABLE D-12
                            CASE STUDY NO. 4
                              CONDITION E:
          CHANGE VANPOOL OCCUPANCY AND ARRIVAL/DEPARTURE RATES

  *  GROSS FLOOR AREA (SQ. FT.)                       1027617
  * SQ, FT. / EMPLOYEE                                    265
  * TOTAL EMPLOYEES                                      3878

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     6.5%         252
     Metrorail/Feeder Bus                    1.0%          39
     Walk/Other                              2.0%          78
     Vanpool                                 9.5%         368
     Auto                                   81.0%        3141
                             total         100.0%        3878

  * AVERAGE DAY EMPLOYEES ( 10% absentees )
     Vanpool                                              332
     Auto                                                2827
                             total                       3158

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                10.00         332         33
     Auto                                    1.25        2827       2262
                             total                                  2295

  * OVERALL OCCUPANCY RATE                   1.38

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              65.00%                   1492
     Non-Employee                          10.00%                    106
            (@ .28 trips/employee)
               Total Inbound Trips                                  1598
              Total Outbound Trips                                   282
          AM Peak Hour 2-way Trips                                  1879

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              60.00%                   1377
     Non-Employee                          12.00%                    130
            (@ .28 trips/employee)
              Total Outbound Trips                                  1507
               Total Inbound Trips                                   266
          PM Peak Hour 2-way Trips                                  1773

  * TRIP RATE / 1000 SQ.  FT. (2-WAY)
     AM Peak Hour                                        1.83
     PM Peak Hour                                        1.73

                                  D-37



                               TABLE D-13
                            CASE STUDY NO. 4
                              CONDITION F:
            REDUCE SQUARE FEET/EMPLOYEE AND VANPOOL OCCUPANCY

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  * SQ. FT. / EMPLOYEE                                    250
  * TOTAL EMPLOYEES                                      4110

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     6.5%         267
     Metrorail/Feeder Bus                    1.0%          41
     Walk/Other                              2.0%          82
     Vanpool                                 9.5%         390
     Auto                                   81.0%        3329
                             total         100.0%        4110

  * AVERAGE DAY EMPLOYEES ( 10% absentees )
     Vanpool                                              351
     Auto                                                2997
                             total                       3348

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                10.00         351         35
     Auto                                    1.25        2997       2397
                             total                                  2432

  * OVERALL OCCUPANCY RATE                   1.38

  AM PEAK HOUR                       ARRIVAL RATE             VEH. TRIPS
  Employee                                 55.00%                   1338
  Non-Employee                             10.00%                    106
     (@ .28 trips/employee,
               Total Inbound Trips                                  1444
              Total Outbound Trips                                   255
     AM Peak Hour 2-way Trips                                       1699

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                   1216
     Non-Employee                          12.00%                    138
            (@ .28 trips/employee)
              Total Outbound Trips                                  1354
               Total Inbound Trips                                   239
          PM Peak Hour 2-way Trips                                  1593

  * TRIP RATE / 1000 SQ.  FT. (2-WAY)
     AM Peak Hour                                        1.65
     PM Peak Hour                                        1.55

                                  D-38



                               TABLE D-14
                            CASE STUDY NO. 4
                              CONDITION G:
        INCREASE SQUARE FEET/EMPLOYEE ; REDUCE VANPOOL OCCUPANCY

  * GROSS FLOOR AREA (SQ. FT.)                        1027617
  * SQ. FT. / EMPLOYEE                                    350
  * TOTAL EMPLOYEES                                      2936

  * MODE OF ARRIVAL                       PERCENT     PERSONS
     Bus                                     6.5%         191
     Metrorail/Feeder Bus                    1.0%          29
     Walk/Other                              2.0%          59
     Vanpool                                 9.5%         279
     Auto                                   81.0%        2378
                             total         100.0%        2936

  * AVERAGE DAY EMPLOYEES ( 10% absentees )
     Vanpool                                              251
     Auto                                                2140
                             total                       2391

  * VEHICLE TRIP ESTIMATES              OCCUPANCY     PERSONS   VEHICLES
     Vanpool                                10.00         251         25
     Auto                                    1.25        2140       1712
                             total                                  1737

  * OVERALL OCCUPANCY RATE                   1.38

  * AM PEAK HOUR                     ARRIVAL RATE             VEH. TRIPS
     Employee                              55.00%                    956
     Non-Employee                          10.00%                    106
            (@ .28 trips/employee)
               Total Inbound Trips                                  1062
              Total Outbound Trips                                   187
          AM Peak Hour 2-way Trips                                  1249

  * PM PEAK HOUR                   DEPARTURE RATE             VEH. TRIPS
     Employee                              50.00%                    869
     Non-Employee                          12.00%                     99
            (@ .28 trips/employee)
              Total Outbound Trips                                   967
               Total Inbound Trips                                   171
          PM Peak Hour 2-way Trips                                  1138

  * TRIP RATE 1000 SQ. FT. (2-WAY)
     AM Peak Hour                                        1.22
     PM Peak Hour                                        1.11

                                  D-39



The objective was to illustrate the impact of listed "default" values
in the office trip generation rate technique in a typical site access
study.  Condition A represents the base condition.  Conditions B and C
evaluate changes in the percentage of employee arrival/departure by
mode to the office complex.  Condition B increases the automobile mode
of arrival by 9% while Condition C deals with a 11% reduction to 70%
arrival by auto as compared to Condition A. Adjustments were made to
the busy metrorail, and walking modes percentages.  Vanpool arrival
percentages were controlled so that overall vehicular occupancy rates
fluctuated inversely with the automobile arrival percentages. 
Condition D lowered the vehicle occupancy rate for automobiles from
1.25 (Condition A) persons per vehicle to 1.1 persons per vehicle This
lowers the overall vehicle occupancy rate from 1.38 to 1:21.

Condition E adjusted the peak hour arrival/departure rates to the
suggested default values, in this case, increasing the percent of
employee trips during the peak hour by 10% from condition A.
Conditions F and G adjusted the assumption of the employee density for
office building types.  For the base Condition A, a 265 square foot
per employee was used.  The default values of 250 and 350 were
substituted along with the other Condition A assumptions and the
appropriate levels of service were determined.

LOS sensitivity Results

A review of Table D-15 indicates that for Conditions A through F while
the office trip generation rates vary significantly between 1.38 and
1.83 (AM) and 1.29 and 1.73 (PM) there is not much variation in the
levels of service at any one of the four intersections.  Location 1
experiences LOS E's intermittently but there is very little difference
between the LOS D's and LOS E's in most instances.  These trip rates
reflected a variation in the mode of arrival/departure, vehicle
occupancy and peak hour arrival/departure.  Condition G however,
reflects the lowest office trip generation rates, 1.22 and 1.11, and
this condition indicated significantly improved level of service
values at all intersections.  These rates reflect an increase in the
number of square feet per employee or a reduction in the number of
employees in the office buildings.

                                  D-40



                               TABLE D-15
                            CASE STUDY NO. 4
                 PEAK HOUR LEVEL-OF-SERVICE COMPARISON:
                         CONDITIONS A THROUGH G

                              Intersection
               1               2              3                4
CONDITION     LOS  VOL        LOS  VOL       LOS  VOL        LOS  VOL

  "A"   AM     D  1239         A   828        B   869         D  1141
        PM     D  1268         C  1011        D  1170         D  1124

  "B"   AM     E  1282         B   883        B   897         D  1171
        PM     E  1290         C  1049        D  1192         D  1131

  "C"   AM     D  1215         A   791        B   869         D  1121
        PM     D  1246         B   967        D  1141         D  1116

  "D"   AM     E               B   897        B   900         D  1178
        PM     E  1296         C  1061        D  1200         D  1134

  "E"   AM     E  1307         B   915        B   907         D  1188
        PM     E  1314         C  1096        D  1223         D  1141

  "F"   AM     D  1271         B   868        B   892         D  1162
        PM     E  1289         C  1047        D  1191         D  1131

  "G"   AM     D  1179         A  7471        B   856         C  1096
        PM     D  1232         B  9401        C  1123         C  1110

                                (PHASING)
                 3 Phase         3 PHASE        3 PHASE        3  PHASE

                        LEVEL OF SERVICE CRITERIA
                             (Vehicles/Hour)
                               3 PHASE

                               LOS
                               A             0 - 855
                               B          855 - 1000
                               C         1000 - 1140
                               D         1140 - 1275
                               E         1275 - 1425
                               F        1425 - ABOVE

                                  D-41



SUMMARY

At location 1, the key intersection studied, the following changes
resulted in less efficient peak hour levels of service, by changing
LOS D to LOS E:

   -  Condition B: increasing the mode of (auto) arrival from 81% to
      90% or reduction in other modes of travel.

   -  Condition D:   reducing the auto vehicle occupancy rate from
      1.25 to 1.1 (reduction in ridesharing)

   -  Condition E:   increasing the arrival/departure rates from 55/50
      to 65/60 (reduction in staggered work hours)

                                  D-42

          * U.S. GOVERNMENT PRINTING OFFICE: 1985-461-816:20505






(380.html)
Jump To Top