Chapter
5 continued from...
It is important for the agency to clearly define lots and sublots when using the prototype PRS. The following definitions are recommended for use. A lot is defined as a discrete quantity of as-constructed pavement to which an acceptance procedure (and corresponding pay adjustment) is applied. All pavement placed within a lot is assumed to have similar characteristics (e.g., traffic loadings, design properties, mix design, support, and representative as-designed AQC distributions). It is recommended that the lot length always be set equal to one day's production unless a significant within-day change occurs in one of the pavement characteristics (e.g., change in aggregate source or stoppage of the paving operations for a significant amount of time). If such a change does occur, it is recommended that a new lot be started at that point in the paving. The lot width is defined as the total width of pavement (one or more traffic lanes) being placed at one time in the mainline paving process. This paving width is also defined as a construction pass since it describes the total width of pavement being placed in one pass of the paving train. (Note: The width of a construction pass can change within a project depending on the number of lanes being paved at one time.) Shoulders are not included in the width of a lot; however, when applicable, the entire width of a widened traffic lane is to be considered as part of the mainline paving. A sublot is simply defined as a portion of a lot. Each lot is divided into sublots of approximately equal surface area, based on the total linear amount of paving expected in the lot. More specifically, within the prototype PRS, sublots represent the smallest unit of pavement for which pavement performance is predicted (from distress indicators). Therefore, sublot lengths are defined so that all AQC's can be independently sampled from each defined sublot. Selecting an Appropriate Target Sublot Length Under the PRS approach, the sublot size is defined in terms of the linear length of longitudinal paving. The minimum sublot length should not be less than 0.16 km; this limit is required to accommodate the measurement of initial smoothness with a California profilograph. Although a maximum sublot length need not be defined, it is recommended that the agency try to select a sublot length that will result in a minimum of three sublots per lot. An appropriate maximum sublot length could then be defined as one-third of the total linear length of longitudinal paving expected for a typical pavement lot (one day of paving). An appropriate sublot length range for a given project can, therefore, be represented by the relationship presented as equation 10.
where
If the maximum sublot length (PAVINGSUBLOT-MAX) is calculated to be less than the chosen minimum sublot length (0.16 km), it is recommended that the chosen sublot length be set to the minimum of 0.16 km. Otherwise, it is recommended that the chosen sublot length be subjectively selected from the computed range (the range shown in equation 10) based on knowledge about the chosen acceptance sampling and testing plan. The agency must determine how many AQC samples and tests are to be taken from each sublot in the field. It is believed that the costs of conducting the required acceptance sampling and testing will greatly influence the selected sublot length. A discussion of the selection of an appropriate acceptance sampling and testing plan is contained in this chapter in the section titled Selecting an AQC Acceptance Sampling and Testing Plan. Determining the Target Number of Sublots Per Lot The target number of sublots per lot is estimated based on the agency-chosen target sublot length (PAVINGSUBLOT) and the estimated total linear length of longitudinal paving for a typical pavement lot (PAVINGLOT). This relationship is shown in equation 11.
where NUMSUBSTARGET = Estimated target number of sublots per lot (based on the chosen target sublot length). As an example, if it were estimated that a contractor would pave 1.2 km per day (PAVINGLOT = 1.2 km) with a target sublot length of 0.32 km (PAVINGSUBLOT = 0.32 km), the target number of sublots per lot (NUMSUBSTARGET) would be calculated as the following (using equation 11). NUMSUBSTARGET = PAVINGLOT / PAVINGSUBLOT For this example, the typical number of sublots per lot would then be three or four. Therefore, the agency should develop preconstruction output for the cases of three and four sublots (as a minimum). More information on choosing appropriate ranges of numbers of sublots per lot is provided in the section titled Selecting Simulation Parameters. Determining Actual Sublot Lengths in the Field Since the amount of paving varies from lot to lot, a method for
dividing the as-constructed pavement lot into sublots is required. The
following defines this procedure.
|