Chapter
4 continued from...
Comparisons of
As-Designed and As-Constructed LCCs |
|
|
Pay adjustments under the revised prototype approach are based on a
direct comparison of representative LCC's determined independently for
both the as-designed and as-constructed pavement lots. Both as-designed
and as-constructed representative lot LCC's are determined using the
procedure described in the previous section.
Project-Specific
Characteristics
The agency begins this comparison for a given project by defining and
fixing those items that will not differ between the as-designed and
as-constructed LCC determinations. These project-specific decisions
include the following:
- Constant Variables—Specific design characteristics grouped
into categories such as traffic, project location and description,
climate, materials, base, and load transfer.
- Definition of Performance—The specific set of distress
indicator models used to define pavement performance. These may include
any or all of the following: transverse slab cracking, transverse joint
faulting, transverse joint spalling, and pavement smoothness over time
(expressed in terms of PSR or IRI).
- Included Acceptance Quality Characteristics—The AQC's that
are sampled and used for acceptance. These may include any or all of the
following: concrete strength, slab thickness, entrained air content,
pavement smoothness, and percent consolidation around dowels.
- Acceptance Sampling and Testing Plan—The specific sampling
and testing procedures used for each of the included AQC's. These
include the sampling and testing methods, number of samples per sublot,
and the timing of sampling.
- Maintenance and Rehabilitation Plan—The defined set of rules
used to predict the type and timing of future M & R
activities.
- Cost-Related Items—The cost-related items associated with the
prediction of future M & R activities. These include items such as
the M & R activity unit costs, percentage of included user costs,
and the selected discount rate.
With all of these project-specific components held constant, the only
variables that may differ between the as-designed and as-constructed
pavements are the means and standard deviations of the chosen AQC's.
Therefore, the difference between the resulting as-designed and
as-constructed lot LCC's is the direct result of differences in the AQC
quality.
Basic Pay
Factor and Pay Adjustment Principles
The actual pay adjustment (incentive or disincentive) for a given lot
is calculated as the difference between the as-designed LCC
(LCCDES) and the as-constructed LCC (LCCCON). This
pay adjustment may be expressed as a percentage of the representative
contractor bid price for the given lot of concrete pavement. This
relationship to the bid price is termed the pay factor (see
equation 3).
Simulation
of the Representative As-Designed Lot LCC
The representative as-designed lot LCC is simulated using the PaveSpec
2.0 computer software. As-designed target AQC means and standard
deviations are selected by the agency and used to define the
agency-desired pavement quality. If the as-constructed pavement is found
to exactly match this desired quality (based on conducted AQC acceptance
sampling and testing), the contractor will receive 100 percent of the
submitted bid price (on average). The PaveSpec 2.0 software is used to
simulate AQC sample sets (from the target AQC distributions) for N
as-designed pavement lots. Each of the N simulated AQC sample sets results
in the calculation of one possible LCC representing the as-designed target
lot. The overall representative as-designed target LCC is, therefore,
computed as the average of the N simulated lot LCC's. This process is
illustrated in figure 7.
|
|
Figure 7. Flow chart showing the process
used to simulate the representative as-designed lot LCC
(LCCDES). |
Level 1 Pay
Adjustments
Simulation of the Level 1 Individual AQC Pay Factor
Curves
The data flow process used to compute the LCC for any
one as-constructed lot is exactly the same as that used to compute the LCC
for any one target as-designed simulated lot. As mentioned previously, the
same constant variables, distress indicator models, acceptance sampling
and testing plan, M & R plan, and cost models are used for both the
as-designed and as-constructed lot simulations. The only difference
between the procedures involves the AQC means and standard deviations used
to define the quality of the as-designed and as-constructed pavement
lots.
If a Level 1 pay adjustment approach is chosen, independent
pay factor charts and corresponding equations are developed for each AQC.
These pay factor charts are developed prior to the bidding on the project
and are made available to the contractor. Hypothetical combinations of
individual AQC means and standard deviations are selected and assumed to
be equal to the as-constructed pavement lot quality. For each hypothetical
combination, a representative as-constructed LCC is simulated using
exactly the same procedure used for the simulation of the representative
as-designed lot LCC (i.e., N AQC sample sets are simulated, resulting in N
computed lot LCC's—the representative as-constructed lot LCC is computed
as the mean of the N simulated as-constructed LCC values). Pay factors
associated with each representative as-constructed LCC (hypothetical
combination of AQC mean and standard deviation) are then determined using
equation 3. (Note: Since these curves must be made available prior to
accepting contractor bids, a representative bid price is used to compute
the pay factors making up these curves [see the section titled Selecting an
Appropriate Bid Price for Developing Level 1 Preconstruction
Output in chapter 5, for more information]). Individual pay factor
curves are constructed for specific levels of AQC standard deviation
(chosen by the agency), and over a chosen range of AQC means, using the
simulated representative as-constructed LCC's. Best-fit regression
equations are then determined, representing the data making up the
individual AQC pay factor curves. An example of a Level 1 pay factor chart
for concrete strength is shown in figure 8.
|
|
Figure 8. Example of an individual Level
1 pay factor chart for concrete
strength. |
It is important to emphasize that only one AQC is allowed to vary at a
time when developing these Level 1 AQC pay factor curves. For example,
when representative pay factors are being simulated for the individual
concrete strength pay factor chart, all simulated pay factors (from
hypothetical combinations of concrete strength mean and standard
deviation) are determined with the other AQC means and standard deviations
(for slab thickness, air content, initial smoothness, and percent
consolidation) set equal to their target values. Figure 9 contains a flow
chart showing the general simulation process used to develop Level 1 AQC
pay factor curves and corresponding pay factor regression equations. A
more detailed step-by-step procedure for generating these Level 1 AQC pay
factor curves and corresponding pay factor regression equations is
presented in chapter 7.
|
|
Figure 9. Flow chart showing the process
used to develop Level 1 AQC pay factor charts and corresponding
equations. |
Level 1 Composite Pay Factors
After the construction of
an actual pavement lot, the agency takes samples from the pavement in
accordance with the chosen acceptance sampling and testing plan. The AQC
sampling and testing values measured in the field (for the given lot) are
summarized into representative lot AQC means and standard deviations. The
lot means and standard deviations are then used in the individual AQC pay
factor regression equations to determine the corresponding independent AQC
pay factors. The procedure used to determine individual AQC Level 1 pay
factors from the pay factor charts is described in more detail in chapter 7.
Finally, the overall representative
as-constructed Level 1 lot pay factor is determined by combining the
individually calculated AQC pay factors into one CPF representing the lot.
The CPF equation essentially provides the appropriate weighting factors
for each independently determined AQC pay factor. This specific CPF
function is determined by the agency. A more detailed discussion of the
commonly used CPF equations is contained in chapter 6 in the section titled Defining a Level 1
Composite Pay Factor Equation. Figure 10 contains a flow chart showing
the general process used to compute a Level 1 lot CPF.
|
|
Figure 10. Flow chart showing the process
used to determine a Level 1 lot composite pay
factor. |
Level 2 Pay
Adjustments
The Level 2 pay adjustment does not require the use of a CPF equation.
The lot pay factor is directly computed through simulation with the
PaveSpec 2.0 software. After the placement of the as-construction pavement
lot, samples are taken from each sublot according to the agency-chosen
acceptance sampling and testing plan. Each set of AQC sublot samples is
then statistically summarized to obtain AQC means representing each
sublot. The sublot means are used in the chosen distress indicators to
predict sublot performance, predicted sublot M & R activities, and
their associated sublot LCC's. Finally, these sublot LCC's are summarized
into one representative lot present worth LCC. The overall as-constructed
lot pay adjustment and pay factor are then determined using this
calculated as-constructed lot LCC in equations 1 and 2,
respectively. Figure 11 contains a flow chart showing the general
simulation process used to calculate a Level 2 lot pay factor.
|
|
Figure 11. Flow chart showing the process
used to determine a Level 2 lot pay
factor. |
Major
Differences Between Level 1 and Level 2 Pay Adjustment
Procedures
Three of the primary differences between the Level 1 and 2 pay
adjustment procedures include the following:
- Preconstruction Output—Individual AQC pay factor curves are
simulated using Level 1 procedures; the only Level 2 preconstruction
output is the simulation of a representative as-designed LCC
(LCCDES).
- Simulation of Pay Factors—Individual Level 1 AQC pay factor
curves are simulated by holding all other AQC's at their target values;
Level 2 pay factors allow for the simultaneous varying of all included
AQC's (i.e., tradeoffs in AQC quality can occur).
- Overall Lot Pay Factor Calculation Method—The overall Level 1
CPF is calculated as a function of the individually determined AQC pay
factors computed using the simulated AQC pay factor charts and
equations; the overall Level 2 pay factor is calculated directly using
equation 3 in this volume. All required LCC's are determined using the
PaveSpec 2.0 software.
It is important to emphasize that the Level 1 lot CPF is actually an
estimate of the computed Level 2 lot pay factor. The Level 2 approach
represents a simulated construction, sampling, testing, performance, and M
& R over many years. Level 1 is a simplified method used to estimate
the same pay factor as determined in Level 2, using more conventional pay
factor curves.
Operating
Characteristic Curves |
|
|
Operating characteristic (OC) curves must be generated by the agency to
determine if the chosen acceptance plan will perform as intended. The OC
curves used with the PRS approach are similar to those used for
conventional accept/reject acceptance plans, except that a set of OC
curves is needed to reflect different payment options.(15) An
example of the OC curves, commonly constructed for adjustable payment
acceptance plans using actual lot percent defective procedures, is
illustrated in figure 12. Each set of OC curves is specific to a chosen
sampling plan (i.e., number of sublots per lot, number of AQC samples per
sublot, and types of AQC samples and tests). The development of these
curves is an integral part of the specification development process in
that they provide the agency and the contractor with information regarding
their respective risk. Similar OC curves can be developed for Level 1
specifications using the PaveSpec 2.0 computer software. The OC curves
developed under the PRS approach are plots of probability of acceptance at
the pay level specified versus AQC mean (rather than percent defective).
More detailed information regarding the development of these curves using
PaveSpec 2.0 is contained in chapter 7 in the section titled Developing
Operating Characteristic Curves.
|
|
Figure 12. Example of typical OC curves
for an adjustable payment acceptance
plan.(15) |
|